Project Summary |
Transportation System: INTRASTATE INTERSTATE | District 03 - Jefferson County |
|
Description: SR 8 (I-10) JEFFERSON COUNTY REST AREA TRUCK PARKING - WB REST AREA | |
|
|
|
|
|
Construction Contract Information
Notice to
Proceed
Date |
Work
Begun
Date |
Present
Contract
Days |
Contract
Days
Used |
Percent
Days
Used |
08/08/2024
|
|
340
|
0
|
0.00%
|
Vendor Name: GOSALIA CONCRETE CONSTRUCTORS, |
|
|
Project Detail |
Fiscal Year: | 2025 | 2026 | 2027 | 2028 | 2029 |
Highways/Preliminary Engineering | (On-Going) |
|
Amount: |
$1,385
|
|
|
|
|
Highways/Railroad & Utilities | (On-Going) |
|
Amount: |
|
|
|
|
|
Highways/Construction | (On-Going) |
|
Amount: |
$15,395
|
|
|
|
|
|
Item Total: | $16,780 | | | | |