| Project Summary |
| Transportation System: INTRASTATE INTERSTATE | District 03 - Jefferson County |
|
| Description: SR 8 (I-10) JEFFERSON COUNTY REST AREA TRUCK PARKING - WB REST AREA | |
|
|
|
|
| |
|
Construction Contract Information
Notice to
Proceed
Date |
Work
Begun
Date |
Present
Contract
Days |
Contract
Days
Used |
Percent
Days
Used |
|
08/08/2024
|
01/20/2025
|
359
|
301
|
83.84%
|
| Vendor Name: GOSALIA CONCRETE CONSTRUCTORS, |
|
| |
| Project Detail |
| Fiscal Year: | 2026 | 2027 | 2028 | 2029 | 2030 |
| Highways/Preliminary Engineering | (On-Going) |
|
|
Amount: |
|
|
|
|
|
| Highways/Railroad & Utilities | (On-Going) |
|
|
Amount: |
|
|
|
|
|
| Highways/Construction | (On-Going) |
|
|
Amount: |
$215,320
|
|
|
|
|
| |
| Item Total: | $215,320 | | | | |