Activity
|
Description
|
Planned
Start
|
Planned
Finish
|
164000000
|
PREPARE SCOPE OF WORK
|
03/01/2019 A
|
04/08/2019 A
|
164010000
|
PREPARE SCOPE OF WORK
|
03/01/2019 A
|
04/08/2020 A
|
155000000
|
UPDATE SCOPE OF WORK
|
04/23/2019 A
|
04/29/2019 A
|
155001000
|
UPDATE SCOPE OF WORK
|
05/07/2019 A
|
05/13/2019 A
|
256000000
|
ORDER DESIGN TRAFFIC
|
06/04/2019 A
|
06/04/2019 A
|
232000000
|
DESIGN CONSULTANT ADVERTISE
|
06/17/2019 A
|
06/17/2019 A
|
459000000
|
LETTERS OF INTEREST
|
07/01/2019 A
|
07/01/2019 A
|
462000000
|
SHORT LIST
|
07/30/2019 A
|
07/30/2019 A
|
249000000
|
TECHNICAL PROPOSAL DUE
|
08/26/2019 A
|
08/26/2019 A
|
402000000
|
CONSULT FINAL SELECTION
|
10/22/2019 A
|
10/22/2019 A
|
230000000
|
CONSULTANT SCOPE MEETING
|
11/15/2019 A
|
11/15/2019 A
|
155002000
|
UPDATE SCOPE OF WORK
|
02/14/2020 A
|
02/16/2020 A
|
233000000
|
P.E. CONTRACT EXECUTED
|
04/08/2020 A
|
04/08/2020 A
|
234000000
|
NOTICE TO PROCEED
|
04/08/2020 A
|
04/14/2020 A
|
106000000
|
DESIGN SURVEY
|
04/15/2020 A
|
05/12/2020 A
|
271001000
|
GEOTECH EVALUATION
|
04/15/2020 A
|
05/12/2020 A
|
381000000
|
PREPARE PHI (30%) DESIGN PLN
|
05/13/2020 A
|
12/21/2020 A
|
235015000
|
SUBMIT PLANS FOR REVIEW
|
07/27/2020 A
|
07/27/2020 A
|
257000000
|
DESIGN TRAFFIC RECEIVED
|
07/31/2020 A
|
07/31/2020 A
|
197000000
|
PAVEMENT DESIGN
|
12/18/2020 A
|
12/18/2020 A
|
235100000
|
SUBMIT PLANS FOR REVIEW
|
01/11/2021 A
|
01/11/2021 A
|
301000000
|
PHASE I PLANS REVIEW
|
01/13/2021 A
|
02/02/2021 A
|
148010000
|
M.O.T. PLANS
|
03/06/2024 A
|
08/12/2024 A
|
264000000
|
UTILITY CONTACT
|
07/03/2024 A
|
07/03/2024 A
|
197001000
|
PAVEMENT DESIGN
|
08/06/2024 A
|
08/06/2024 A
|
148000000
|
M.O.T. PLANS
|
08/12/2024 A
|
08/12/2024 A
|
148020000
|
M.O.T. PLANS
|
08/13/2024 A
|
08/28/2024 A
|
260000000
|
TYPICAL SECTION APPROVED
|
08/30/2024 A
|
02/28/2025 A
|
382000000
|
PREPARE PHII (60%) DESIGN PLN
|
09/03/2024 A
|
11/25/2024 A
|
271000000
|
GEOTECH EVALUATION
|
09/03/2024 A
|
03/17/2025 A
|
197002000
|
PAVEMENT DESIGN
|
09/05/2024 A
|
12/30/2024 A
|
750000000
|
WETLAND REPORT
|
09/19/2024 A
|
09/25/2024 A
|
750001000
|
WETLAND REPORT
|
09/26/2024 A
|
10/31/2024 A
|
235200000
|
SUBMIT PLANS FOR REVIEW
|
12/16/2024 A
|
12/16/2024 A
|
302000000
|
PHASE II PLANS REVIEW
|
12/16/2024 A
|
01/06/2025 A
|
242300000
|
SPECIFICATIONS
|
12/27/2024 A
|
03/12/2025 A
|
264001000
|
UTILITY CONTACT
|
01/06/2025 A
|
01/06/2025 A
|
265000000
|
UTILITY PRE-DESIGN CONF
|
01/07/2025 A
|
01/07/2025 A
|
383000000
|
PREPARE PHIII (90%) DESIGN PLN
|
01/21/2025 A
|
03/06/2025 A
|
233321000
|
P.E. CONTRACT EXECUTED
|
02/14/2025 A
|
02/14/2025 A
|
297200000
|
CONST. ESTIMATE UPDATE
|
03/07/2025 A
|
03/12/2025 A
|
235300000
|
SUBMIT PLANS FOR REVIEW
|
03/17/2025 A
|
03/17/2025 A
|
303000000
|
PHASE III PLANS REVIEW
|
03/18/2025 A
|
03/31/2025 A
|
383001000
|
PREPARE PHIII (90%) DESIGN PLN
|
05/05/2025 A
|
09/05/2025
|
279000000
|
RAILROAD CLEAR
|
07/01/2025
|
09/10/2025
|
236000000
|
FINAL EVALUATION OF CONSULT
|
07/01/2025
|
Fiscal Year: 2028
|
235301000
|
SUBMIT PLANS FOR REVIEW
|
09/23/2025
|
09/23/2025
|
264002000
|
UTILITY CONTACT
|
09/23/2025
|
09/23/2025
|
303001000
|
PHASE III PLANS REVIEW
|
09/24/2025
|
09/26/2025
|
384000000
|
PREPARE PHIV (100%) DESIGN PLN
|
09/24/2025
|
10/02/2025
|
242400000
|
SPECIFICATIONS
|
09/24/2025
|
10/24/2025
|
235400000
|
SUBMIT PLANS FOR REVIEW
|
10/27/2025
|
10/27/2025
|
219000000
|
WATER MNGMT DIST PERMITS
|
10/27/2025
|
12/08/2025
|
310000000
|
PHASE IV PLANS REVIEW
|
10/28/2025
|
11/10/2025
|
355000000
|
NMSA (NON MAJOR STATE ACTION)
|
10/28/2025
|
12/08/2025
|
222000000
|
ALL PERMITS CLEAR
|
10/28/2025
|
12/09/2025
|
187000000
|
NO R/W REQRD CERTIFICATION
|
10/28/2025
|
12/09/2025
|
405000000
|
CEI CONSULTANT ADVERTISE
|
11/03/2025
|
03/23/2026
|
205000000
|
CNST UTILITY CONTRACT EXECUTED
|
11/17/2025
|
11/17/2025
|
228000000
|
SUBMIT UTILITY DATA
|
11/18/2025
|
11/19/2025
|
332000000
|
EARLY NOTIFICATION PROCESS
|
11/18/2025
|
12/09/2025
|
226000000
|
PLANS TO DIST SPECS
|
11/21/2025
|
11/21/2025
|
204000000
|
PRODUCTION DATE
|
12/10/2025
|
12/10/2025
|
242030000
|
SPECIFICATIONS
|
12/11/2025
|
12/26/2025
|
266000000
|
UTILITIES CERTIFIED
|
12/18/2025
|
12/18/2025
|
203000000
|
C.E.I. CONS. CONT. EXEC.
|
12/18/2025
|
05/05/2026
|
370000000
|
PLANS TO DIST CONTRACT
|
12/26/2025
|
12/26/2025
|
229000000
|
ADVERTISE DISTRICT CONTRACT
|
01/12/2026
|
02/09/2026
|
280000000
|
LETTING DATE
|
02/10/2026
|
02/10/2026
|
238000000
|
INTERIM EVALUATION OF CONSULT
|
02/11/2026
|
Fiscal Year: 2028
|
202010000
|
POST DESIGN SERVICES
|
05/06/2026
|
Fiscal Year: 2028
|
312000000
|
CONSTRUCTION
|
05/06/2026
|
Fiscal Year: 2028
|