Activity
|
Description
|
Planned
Start
|
Planned
Finish
|
299010000
|
REQUEST FOR AUTHORIZATION
|
11/29/2021 A
|
11/29/2021 A
|
164010000
|
PREPARE SCOPE OF WORK
|
12/31/2021 A
|
01/13/2022 A
|
231010000
|
SUBMIT CONSULTANT PACKAGE
|
01/03/2022 A
|
01/03/2022 A
|
232010000
|
DESIGN CONSULTANT ADVERTISE
|
01/18/2022 A
|
01/18/2022 A
|
402010000
|
CONSULT FINAL SELECTION
|
03/21/2022 A
|
03/21/2022 A
|
164030000
|
PREPARE SCOPE OF WORK
|
04/25/2022 A
|
05/04/2022 A
|
233010000
|
P.E. CONTRACT EXECUTED
|
05/26/2022 A
|
05/26/2022 A
|
298010000
|
R/W ESTIMATE UPDATE
|
06/08/2022 A
|
06/08/2022 A
|
250010000
|
P.E. BEGIN
|
06/15/2022 A
|
06/15/2022 A
|
325020000
|
TIITF & OTHER GOV DOC
|
06/16/2022 A
|
06/16/2022 A
|
170010000
|
R/W CONTROL SURVEY
|
06/16/2022 A
|
04/05/2023 A
|
106010000
|
DESIGN SURVEY
|
06/17/2022 A
|
12/01/2022 A
|
256010000
|
ORDER DESIGN TRAFFIC
|
06/21/2022 A
|
06/21/2022 A
|
257010000
|
DESIGN TRAFFIC RECEIVED
|
06/29/2022 A
|
06/29/2022 A
|
290010000
|
COMMUNITY AWARE PLAN COMPLETE
|
07/07/2022 A
|
07/22/2022 A
|
106210000
|
DESIGN SURVEY
|
07/14/2022 A
|
10/07/2022 A
|
264000000
|
UTILITY CONTACT
|
07/20/2022 A
|
07/20/2022 A
|
424020000
|
R/W SCOPE OF WORK
|
07/26/2022 A
|
07/26/2022 A
|
146005000
|
TITLE SEARCH WORK
|
08/01/2022 A
|
08/01/2022 A
|
106310000
|
DESIGN SURVEY
|
09/13/2022 A
|
11/04/2022 A
|
170150000
|
R/W CONTROL SURVEY
|
11/07/2022 A
|
12/30/2022 A
|
106110000
|
DESIGN SURVEY
|
12/02/2022 A
|
12/02/2022 A
|
315020000
|
R/W CONTROL MAP
|
01/02/2023 A
|
01/27/2023 A
|
315120000
|
R/W CONTROL MAP
|
01/02/2023 A
|
03/21/2023 A
|
221010000
|
ACCESS MANAGEMENT REVIEW
|
01/24/2023 A
|
02/20/2023 A
|
113010000
|
ROADWAY PLANS
|
02/17/2023 A
|
04/28/2023 A
|
367010000
|
DEVELOP PREFERRED ALIGNMENT
|
02/17/2023 A
|
01/11/2024 A
|
372010000
|
SUBMIT PAVE TYPE RPT 30% (PH1)
|
03/14/2023 A
|
03/14/2023 A
|
109110000
|
DRAINAGE DESIGN
|
03/22/2023 A
|
03/22/2023 A
|
145040000
|
PERMITS
|
03/22/2023 A
|
03/22/2023 A
|
315030000
|
R/W CONTROL MAP
|
03/22/2023 A
|
04/18/2023 A
|
298090000
|
R/W ESTIMATE UPDATE
|
04/13/2023 A
|
04/13/2023 A
|
315140000
|
R/W CONTROL MAP
|
04/19/2023 A
|
05/30/2023 A
|
304010000
|
CORING
|
05/01/2023 A
|
05/22/2023 A
|
315040000
|
R/W CONTROL MAP
|
05/31/2023 A
|
06/27/2023 A
|
313010000
|
TEST RESULTS RECEIVED
|
06/26/2023 A
|
06/26/2023 A
|
138010000
|
R/W PRELIMINARY MAP
|
06/28/2023 A
|
07/25/2023 A
|
140010000
|
REVIEW CONSULTANT R/W MAP
|
07/26/2023 A
|
08/22/2023 A
|
131010000
|
ROADWAY SOILS SURVEY
|
08/02/2023 A
|
01/05/2024 A
|
139010000
|
FINAL R/W MAP
|
08/23/2023 A
|
08/05/2024 A
|
197010000
|
PAVEMENT DESIGN
|
09/20/2023 A
|
09/25/2023 A
|
294010000
|
PROCESS EXCEPTIONS/VARIANCE
|
09/20/2023 A
|
09/25/2023 A
|
294020000
|
PROCESS EXCEPTIONS/VARIANCE
|
09/25/2023 A
|
11/21/2023 A
|
197030000
|
PAVEMENT DESIGN
|
09/26/2023 A
|
10/23/2023 A
|
197015000
|
PAVEMENT DESIGN
|
10/26/2023 A
|
02/15/2024 A
|
121010000
|
NEGOTIATION
|
10/30/2023 A
|
10/16/2025
|
113020000
|
ROADWAY PLANS
|
11/02/2023 A
|
02/27/2024 A
|
424010000
|
R/W SCOPE OF WORK
|
11/20/2023 A
|
11/20/2023 A
|
109010000
|
DRAINAGE DESIGN
|
11/20/2023 A
|
02/27/2024 A
|
367020000
|
DEVELOP PREFERRED ALIGNMENT
|
01/11/2024 A
|
01/11/2024 A
|
197020000
|
PAVEMENT DESIGN
|
01/22/2024 A
|
01/22/2024 A
|
138030000
|
R/W PRELIMINARY MAP
|
02/15/2024 A
|
06/18/2024 A
|
197040000
|
PAVEMENT DESIGN
|
02/15/2024 A
|
05/16/2025 A
|
302010000
|
PHASE II PLANS REVIEW
|
02/29/2024 A
|
03/28/2024 A
|
260010000
|
TYPICAL SECTION APPROVED
|
03/11/2024 A
|
03/11/2024 A
|
302040000
|
PHASE II PLANS REVIEW
|
03/29/2024 A
|
04/11/2024 A
|
113030000
|
ROADWAY PLANS
|
04/11/2024 A
|
10/14/2024 A
|
265010000
|
UTILITY PRE-DESIGN CONF
|
04/25/2024 A
|
04/25/2024 A
|
302030000
|
PHASE II PLANS REVIEW
|
04/25/2024 A
|
05/01/2024 A
|
238020000
|
INTERIM EVALUATION OF CONSULT
|
04/25/2024 A
|
10/29/2024 A
|
264005000
|
UTILITY CONTACT
|
05/09/2024 A
|
09/25/2024 A
|
145010000
|
PERMITS
|
05/13/2024 A
|
08/19/2024 A
|
272010000
|
FILE PERMITS
|
05/14/2024 A
|
12/06/2024 A
|
322020000
|
R/W REQUIRE. TO R/W ENG.
|
06/17/2024 A
|
06/17/2024 A
|
268010000
|
DOCUMENTS TO R/W
|
07/03/2024 A
|
07/03/2024 A
|
144010000
|
INSTRUMENT PREP
|
07/03/2024 A
|
07/03/2024 A
|
208010000
|
APPRAISAL CONTRACT
|
08/01/2024 A
|
10/31/2024 A
|
140020000
|
REVIEW CONSULTANT R/W MAP
|
08/06/2024 A
|
08/14/2024 A
|
315050000
|
R/W CONTROL MAP
|
08/14/2024 A
|
08/14/2024 A
|
131020000
|
ROADWAY SOILS SURVEY
|
08/19/2024 A
|
10/15/2024 A
|
157010000
|
R/W MAP COMPLETE
|
08/20/2024 A
|
08/20/2024 A
|
349010000
|
PH 4B ROW SERVCE CONTRACT EXEC
|
09/24/2024 A
|
09/24/2024 A
|
120010000
|
APPRAISALS
|
10/10/2024 A
|
11/07/2024 A
|
303010000
|
PHASE III PLANS REVIEW
|
10/15/2024 A
|
11/12/2024 A
|
129010000
|
RELOCATION WORK
|
10/23/2024 A
|
01/02/2026
|
143010000
|
APPRAISAL REVIEW
|
11/07/2024 A
|
12/18/2024 A
|
303030000
|
PHASE III PLANS REVIEW
|
11/12/2024 A
|
11/26/2024 A
|
164430000
|
PREPARE SCOPE OF WORK
|
03/17/2025 A
|
03/18/2025 A
|
279010000
|
RAILROAD CLEAR
|
04/15/2025 A
|
04/15/2025 A
|
222010000
|
ALL PERMITS CLEAR
|
05/01/2025 A
|
05/01/2025 A
|
250410000
|
P.E. BEGIN
|
06/10/2025 A
|
06/10/2025 A
|
310410000
|
PHASE IV PLANS REVIEW
|
06/12/2025 A
|
11/12/2025
|
264010000
|
UTILITY CONTACT
|
06/24/2025 A
|
12/16/2025
|
329020000
|
ENVIRONMENTAL REVIEW
|
06/30/2025
|
08/01/2025
|
359020000
|
COMMUNITY INVOLVEMENT
|
06/30/2025
|
12/10/2025
|
240010000
|
COMPILE SUIT DATA
|
07/31/2025
|
07/31/2025
|
303210000
|
PHASE III PLANS REVIEW
|
09/23/2025
|
12/10/2025
|
310010000
|
PHASE IV PLANS REVIEW
|
10/21/2025
|
01/15/2026
|
201010000
|
PLANS COMPLETED
|
11/25/2025
|
01/15/2026
|
131030000
|
ROADWAY SOILS SURVEY
|
11/25/2025
|
01/15/2026
|
106040000
|
DESIGN SURVEY
|
11/26/2025
|
01/16/2026
|
204010000
|
PRODUCTION DATE
|
02/16/2026
|
02/16/2026
|
226010000
|
PLANS TO DIST SPECS
|
02/16/2026
|
03/02/2026
|
242010000
|
SPECIFICATIONS
|
02/16/2026
|
03/23/2026
|
273010000
|
FINAL R/W ORDER OF TAKING
|
02/19/2026
|
02/19/2026
|
264440000
|
UTILITY CONTACT
|
03/03/2026
|
03/16/2026
|
266010000
|
UTILITIES CERTIFIED
|
03/17/2026
|
03/17/2026
|
205010000
|
CNST UTILITY CONTRACT EXECUTED
|
03/17/2026
|
05/26/2026
|
171010000
|
REQUEST CONTRACT TIME
|
03/18/2026
|
04/02/2026
|
212010000
|
TRANSMIT PKG FOR LETTING
|
03/23/2026
|
03/23/2026
|
310020000
|
PHASE IV PLANS REVIEW
|
04/03/2026
|
04/03/2026
|
203010000
|
C.E.I. CONS. CONT. EXEC.
|
05/04/2026
|
05/04/2026
|
125010000
|
R/W DEMO & CLEAR WORK
|
05/08/2026
|
06/18/2026
|
280010000
|
LETTING DATE
|
05/27/2026
|
05/27/2026
|
300230000
|
RIGHT OF WAY SURVEY
|
05/28/2026
|
06/19/2026
|
255010000
|
R/W CERTIFIED
|
06/19/2026
|
06/19/2026
|