Scheduled Activities may or
may not be confirmed dates and are subject to change without notice.
Please contact the Program Services Office at the appropriate
District office for validation.
|
|
|
452154-1
|
I-75 AT JONES LOOP TRUCK PARKING
|
District 01 - Charlotte County
|
Project Manager: NEM-AEB-UVV |
|
Type of Work: PARKING FACILITY |
|
|
Activity
|
Description
|
Planned
Start
|
Planned
Finish
|
|
233000000
|
P.E. CONTRACT EXECUTED
|
04/04/2024 A
|
04/04/2024 A
|
|
106000000
|
DESIGN SURVEY
|
04/13/2024 A
|
07/01/2024 A
|
|
250000000
|
P.E. BEGIN
|
05/01/2024 A
|
05/01/2024 A
|
|
265020000
|
UTILITY PRE-DESIGN CONF
|
07/18/2024 A
|
07/18/2024 A
|
|
168120000
|
Q. A. REVIEW
|
08/01/2024 A
|
08/01/2024 A
|
|
109510000
|
DRAINAGE DESIGN
|
09/12/2024 A
|
09/12/2024 A
|
|
271440000
|
GEOTECH EVALUATION
|
10/01/2024 A
|
12/13/2024 A
|
|
271040000
|
GEOTECH EVALUATION
|
10/15/2024 A
|
11/15/2024 A
|
|
132120000
|
ROADWAY SOILS REPORT
|
01/03/2025 A
|
04/04/2025 A
|
|
264011330
|
UTILITY CONTACT
|
01/08/2025 A
|
01/08/2025 A
|
|
264040000
|
UTILITY CONTACT
|
01/08/2025 A
|
03/03/2025 A
|
|
132110000
|
ROADWAY SOILS REPORT
|
01/15/2025 A
|
01/15/2025 A
|
|
228130000
|
SUBMIT UTILITY DATA
|
01/15/2025 A
|
07/17/2025 A
|
|
132000000
|
ROADWAY SOILS REPORT
|
01/15/2025 A
|
08/28/2025 A
|
|
113200000
|
ROADWAY PLANS
|
01/15/2025 A
|
08/29/2025 A
|
|
197020000
|
PAVEMENT DESIGN
|
04/01/2025 A
|
08/25/2025 A
|
|
228009220
|
SUBMIT UTILITY DATA
|
05/27/2025 A
|
08/28/2025 A
|
|
228001070
|
SUBMIT UTILITY DATA
|
06/27/2025 A
|
08/28/2025 A
|
|
131000000
|
ROADWAY SOILS SURVEY
|
07/28/2025 A
|
08/27/2025 A
|
|
228001220
|
SUBMIT UTILITY DATA
|
07/28/2025 A
|
08/28/2025 A
|
|
102210000
|
TRAFFIC STUDIES
|
08/04/2025 A
|
08/04/2025 A
|
|
302100000
|
PHASE II PLANS REVIEW
|
08/29/2025 A
|
09/29/2025 A
|
|
113011270
|
ROADWAY PLANS
|
09/30/2025 A
|
10/13/2025 A
|
|
235240000
|
SUBMIT PLANS FOR REVIEW
|
11/17/2025 A
|
11/17/2025 A
|
|
228011450
|
SUBMIT UTILITY DATA
|
12/09/2025 A
|
12/09/2025 A
|
|
159300000
|
COLOR CODE UTILITY PLANS
|
12/09/2025 A
|
01/30/2026 A
|
|
264001550
|
UTILITY CONTACT
|
01/08/2026 A
|
01/08/2026 A
|
|
113300000
|
ROADWAY PLANS
|
01/08/2026 A
|
03/20/2026 A
|
|
272000000
|
FILE PERMITS
|
02/20/2026 A
|
02/20/2026 A
|
|
145020000
|
PERMITS
|
02/20/2026 A
|
04/14/2027
|
|
113370000
|
ROADWAY PLANS
|
03/30/2026 A
|
07/07/2026
|
|
264019800
|
UTILITY CONTACT
|
04/10/2026
|
05/15/2026
|
|
145400000
|
PERMITS
|
04/10/2026
|
10/19/2026
|
|
128070000
|
ASBESTOS SURVEY/ABATEMENT
|
04/10/2026
|
11/17/2026
|
|
336310000
|
ENVIRONMENTAL REEVALUATION
|
04/10/2026
|
Fiscal Year: 2028
|
|
290220000
|
COMMUNITY AWARE PLAN COMPLETE
|
04/10/2026
|
Fiscal Year: 2028
|
|
290270000
|
COMMUNITY AWARE PLAN COMPLETE
|
04/10/2026
|
Fiscal Year: 2028
|
|
168140000
|
Q. A. REVIEW
|
04/10/2026
|
Fiscal Year: 2028
|
|
197100000
|
PAVEMENT DESIGN
|
04/10/2026
|
Fiscal Year: 2028
|
|
132440000
|
ROADWAY SOILS REPORT
|
04/10/2026
|
Fiscal Year: 2028
|
|
264011680
|
UTILITY CONTACT
|
04/13/2026
|
06/15/2026
|
|
145450000
|
PERMITS
|
04/13/2026
|
04/14/2027
|
|
290290000
|
COMMUNITY AWARE PLAN COMPLETE
|
05/08/2026
|
Fiscal Year: 2028
|
|
168190000
|
Q. A. REVIEW
|
05/08/2026
|
Fiscal Year: 2028
|
|
228009320
|
SUBMIT UTILITY DATA
|
05/11/2026
|
07/07/2026
|
|
264011960
|
UTILITY CONTACT
|
05/11/2026
|
07/07/2026
|
|
303100000
|
PHASE III PLANS REVIEW
|
05/26/2026
|
12/04/2026
|
|
264013960
|
UTILITY CONTACT
|
06/02/2026
|
07/08/2026
|
|
868670000
|
JPA PREPARED
|
06/03/2026
|
08/19/2026
|
|
228400000
|
SUBMIT UTILITY DATA
|
06/03/2026
|
09/18/2026
|
|
336330000
|
ENVIRONMENTAL REEVALUATION
|
06/10/2026
|
Fiscal Year: 2028
|
|
128090000
|
ASBESTOS SURVEY/ABATEMENT
|
06/22/2026
|
12/04/2026
|
|
264019900
|
UTILITY CONTACT
|
07/16/2026
|
08/20/2026
|
|
264012680
|
UTILITY CONTACT
|
07/17/2026
|
09/18/2026
|
|
264019960
|
UTILITY CONTACT
|
08/14/2026
|
09/21/2026
|
|
264012960
|
UTILITY CONTACT
|
08/17/2026
|
10/19/2026
|
|
264011970
|
UTILITY CONTACT
|
09/15/2026
|
11/09/2026
|
|
228001960
|
SUBMIT UTILITY DATA
|
10/06/2026
|
12/03/2026
|
|
171000000
|
REQUEST CONTRACT TIME
|
10/27/2026
|
12/04/2026
|
|
171200000
|
REQUEST CONTRACT TIME
|
10/28/2026
|
01/04/2027
|
|
113400000
|
ROADWAY PLANS
|
10/28/2026
|
01/04/2027
|
|
310100000
|
PHASE IV PLANS REVIEW
|
11/30/2026
|
01/19/2027
|
|
255000000
|
R/W CERTIFIED
|
12/01/2026
|
04/15/2027
|
|
113011470
|
ROADWAY PLANS
|
12/14/2026
|
03/17/2027
|
|
336510000
|
ENVIRONMENTAL REEVALUATION
|
12/14/2026
|
03/18/2027
|
|
264013970
|
UTILITY CONTACT
|
12/14/2026
|
03/30/2027
|
|
163050000
|
MAINT OR FUNDS AGREEMENT
|
12/14/2026
|
04/15/2027
|
|
228400010
|
SUBMIT UTILITY DATA
|
12/15/2026
|
04/13/2027
|
|
113500000
|
ROADWAY PLANS
|
12/15/2026
|
04/14/2027
|
|
336530000
|
ENVIRONMENTAL REEVALUATION
|
12/21/2026
|
04/15/2027
|
|
269000000
|
ALL UTILITIES CLEAR
|
12/30/2026
|
04/14/2027
|
|
266000000
|
UTILITIES CERTIFIED
|
12/31/2026
|
04/15/2027
|
|
235500000
|
SUBMIT PLANS FOR REVIEW
|
01/13/2027
|
04/15/2027
|
|
235530000
|
SUBMIT PLANS FOR REVIEW
|
01/13/2027
|
Fiscal Year: 2028
|
|
279000000
|
RAILROAD CLEAR
|
02/05/2027
|
02/05/2027
|
|
226000000
|
PLANS TO DIST SPECS
|
04/19/2027
|
04/19/2027
|
|
242000000
|
SPECIFICATIONS
|
04/19/2027
|
05/31/2027
|
|
222000000
|
ALL PERMITS CLEAR
|
04/23/2027
|
04/23/2027
|
|
278000000
|
ADVERTISMENT FOR LETTING
|
06/28/2027
|
06/28/2027
|
|
278220000
|
ADVERTISMENT FOR LETTING
|
06/28/2027
|
Fiscal Year: 2028
|
|
|
|