Activity
|
Description
|
Planned
Start
|
Planned
Finish
|
233000000
|
P.E. CONTRACT EXECUTED
|
04/04/2024 A
|
04/04/2024 A
|
106000000
|
DESIGN SURVEY
|
04/13/2024 A
|
07/01/2024 A
|
250000000
|
P.E. BEGIN
|
05/01/2024 A
|
05/01/2024 A
|
265020000
|
UTILITY PRE-DESIGN CONF
|
07/18/2024 A
|
07/18/2024 A
|
109510000
|
DRAINAGE DESIGN
|
09/12/2024 A
|
09/12/2024 A
|
271440000
|
GEOTECH EVALUATION
|
10/01/2024 A
|
12/13/2024 A
|
271040000
|
GEOTECH EVALUATION
|
10/15/2024 A
|
11/15/2024 A
|
264011330
|
UTILITY CONTACT
|
01/08/2025 A
|
01/08/2025 A
|
264040000
|
UTILITY CONTACT
|
01/08/2025 A
|
03/03/2025 A
|
102210000
|
TRAFFIC STUDIES
|
04/18/2025
|
06/19/2025
|
290220000
|
COMMUNITY AWARE PLAN COMPLETE
|
04/18/2025
|
08/18/2025
|
260020000
|
TYPICAL SECTION APPROVED
|
04/18/2025
|
08/19/2025
|
132000000
|
ROADWAY SOILS REPORT
|
04/18/2025
|
09/17/2025
|
267000000
|
RAILROAD CONTACT
|
04/18/2025
|
01/20/2026
|
299310000
|
REQUEST FOR AUTHORIZATION
|
04/18/2025
|
Fiscal Year: 2027
|
228130000
|
SUBMIT UTILITY DATA
|
04/18/2025
|
Fiscal Year: 2027
|
132110000
|
ROADWAY SOILS REPORT
|
04/18/2025
|
Fiscal Year: 2027
|
336310000
|
ENVIRONMENTAL REEVALUATION
|
04/18/2025
|
Fiscal Year: 2028
|
168120000
|
Q. A. REVIEW
|
04/18/2025
|
Fiscal Year: 2028
|
115630000
|
BRIDGE PLANS
|
04/18/2025
|
Fiscal Year: 2028
|
299320000
|
REQUEST FOR AUTHORIZATION
|
04/18/2025
|
Fiscal Year: 2028
|
210240000
|
REVIEW PRELIM R/W REQUIREMENTS
|
04/18/2025
|
Fiscal Year: 2028
|
154100000
|
PAVEMENT SURVEY REPORT
|
04/21/2025
|
06/20/2025
|
281000000
|
SUBMIT RR DATA
|
04/21/2025
|
02/03/2026
|
132120000
|
ROADWAY SOILS REPORT
|
04/21/2025
|
Fiscal Year: 2028
|
197020000
|
PAVEMENT DESIGN
|
04/22/2025
|
07/21/2025
|
290270000
|
COMMUNITY AWARE PLAN COMPLETE
|
05/16/2025
|
09/16/2025
|
260080000
|
TYPICAL SECTION APPROVED
|
05/16/2025
|
09/17/2025
|
168140000
|
Q. A. REVIEW
|
05/16/2025
|
Fiscal Year: 2028
|
232900000
|
DESIGN CONSULTANT ADVERTISE
|
05/16/2025
|
Fiscal Year: 2028
|
197080000
|
PAVEMENT DESIGN
|
05/20/2025
|
09/16/2025
|
336330000
|
ENVIRONMENTAL REEVALUATION
|
05/28/2025
|
Fiscal Year: 2028
|
228001220
|
SUBMIT UTILITY DATA
|
06/16/2025
|
07/15/2025
|
290290000
|
COMMUNITY AWARE PLAN COMPLETE
|
06/16/2025
|
09/17/2025
|
128010000
|
ASBESTOS SURVEY/ABATEMENT
|
06/16/2025
|
Fiscal Year: 2027
|
168190000
|
Q. A. REVIEW
|
06/16/2025
|
Fiscal Year: 2028
|
131000000
|
ROADWAY SOILS SURVEY
|
06/17/2025
|
Fiscal Year: 2028
|
228001070
|
SUBMIT UTILITY DATA
|
07/08/2025
|
09/10/2025
|
128030000
|
ASBESTOS SURVEY/ABATEMENT
|
07/15/2025
|
Fiscal Year: 2027
|
197100000
|
PAVEMENT DESIGN
|
07/17/2025
|
09/17/2025
|
132440000
|
ROADWAY SOILS REPORT
|
07/30/2025
|
Fiscal Year: 2028
|
128070000
|
ASBESTOS SURVEY/ABATEMENT
|
08/12/2025
|
Fiscal Year: 2028
|
113200000
|
ROADWAY PLANS
|
08/14/2025
|
09/17/2025
|
228009220
|
SUBMIT UTILITY DATA
|
09/03/2025
|
10/01/2025
|
128090000
|
ASBESTOS SURVEY/ABATEMENT
|
10/22/2025
|
Fiscal Year: 2028
|
302100000
|
PHASE II PLANS REVIEW
|
12/10/2025
|
12/23/2025
|
235240000
|
SUBMIT PLANS FOR REVIEW
|
12/24/2025
|
01/23/2026
|
113011270
|
ROADWAY PLANS
|
12/24/2025
|
03/31/2026
|
228011450
|
SUBMIT UTILITY DATA
|
01/26/2026
|
01/26/2026
|
113300000
|
ROADWAY PLANS
|
01/26/2026
|
04/10/2026
|
264001550
|
UTILITY CONTACT
|
03/10/2026
|
03/10/2026
|
159300000
|
COLOR CODE UTILITY PLANS
|
03/11/2026
|
04/16/2026
|
868240000
|
JPA PREPARED
|
03/25/2026
|
03/25/2026
|
868460000
|
JPA PREPARED
|
03/26/2026
|
05/20/2026
|
145400000
|
PERMITS
|
04/10/2026
|
Fiscal Year: 2027
|
145450000
|
PERMITS
|
04/13/2026
|
Fiscal Year: 2027
|
272000000
|
FILE PERMITS
|
04/17/2026
|
04/17/2026
|
113370000
|
ROADWAY PLANS
|
04/20/2026
|
06/08/2026
|
145020000
|
PERMITS
|
04/20/2026
|
Fiscal Year: 2027
|
868530000
|
JPA PREPARED
|
05/21/2026
|
05/21/2026
|
868540000
|
JPA PREPARED
|
05/22/2026
|
05/22/2026
|
868660000
|
JPA PREPARED
|
05/26/2026
|
Fiscal Year: 2027
|
303100000
|
PHASE III PLANS REVIEW
|
06/16/2026
|
Fiscal Year: 2027
|
264019800
|
UTILITY CONTACT
|
Fiscal Year: 2027
|
Fiscal Year: 2027
|
264011680
|
UTILITY CONTACT
|
Fiscal Year: 2027
|
Fiscal Year: 2027
|
264011960
|
UTILITY CONTACT
|
Fiscal Year: 2027
|
Fiscal Year: 2027
|
228009320
|
SUBMIT UTILITY DATA
|
Fiscal Year: 2027
|
Fiscal Year: 2027
|
264013960
|
UTILITY CONTACT
|
Fiscal Year: 2027
|
Fiscal Year: 2027
|
228400000
|
SUBMIT UTILITY DATA
|
Fiscal Year: 2027
|
Fiscal Year: 2027
|
868670000
|
JPA PREPARED
|
Fiscal Year: 2027
|
Fiscal Year: 2027
|
264019900
|
UTILITY CONTACT
|
Fiscal Year: 2027
|
Fiscal Year: 2027
|
264012680
|
UTILITY CONTACT
|
Fiscal Year: 2027
|
Fiscal Year: 2027
|
868750000
|
JPA PREPARED
|
Fiscal Year: 2027
|
Fiscal Year: 2027
|
264019960
|
UTILITY CONTACT
|
Fiscal Year: 2027
|
Fiscal Year: 2027
|
264012960
|
UTILITY CONTACT
|
Fiscal Year: 2027
|
Fiscal Year: 2027
|
264011970
|
UTILITY CONTACT
|
Fiscal Year: 2027
|
Fiscal Year: 2027
|
228001960
|
SUBMIT UTILITY DATA
|
Fiscal Year: 2027
|
Fiscal Year: 2027
|
171000000
|
REQUEST CONTRACT TIME
|
Fiscal Year: 2027
|
Fiscal Year: 2027
|
171200000
|
REQUEST CONTRACT TIME
|
Fiscal Year: 2027
|
Fiscal Year: 2027
|
113400000
|
ROADWAY PLANS
|
Fiscal Year: 2027
|
Fiscal Year: 2027
|
310100000
|
PHASE IV PLANS REVIEW
|
Fiscal Year: 2027
|
Fiscal Year: 2027
|
336530000
|
ENVIRONMENTAL REEVALUATION
|
Fiscal Year: 2027
|
Fiscal Year: 2028
|
113011470
|
ROADWAY PLANS
|
Fiscal Year: 2027
|
Fiscal Year: 2027
|
264013970
|
UTILITY CONTACT
|
Fiscal Year: 2027
|
Fiscal Year: 2027
|
163050000
|
MAINT OR FUNDS AGREEMENT
|
Fiscal Year: 2027
|
Fiscal Year: 2027
|
279000000
|
RAILROAD CLEAR
|
Fiscal Year: 2027
|
Fiscal Year: 2027
|
336510000
|
ENVIRONMENTAL REEVALUATION
|
Fiscal Year: 2027
|
Fiscal Year: 2028
|
113500000
|
ROADWAY PLANS
|
Fiscal Year: 2027
|
Fiscal Year: 2027
|
228400010
|
SUBMIT UTILITY DATA
|
Fiscal Year: 2027
|
Fiscal Year: 2027
|
204000000
|
PRODUCTION DATE
|
Fiscal Year: 2027
|
Fiscal Year: 2027
|
226000000
|
PLANS TO DIST SPECS
|
Fiscal Year: 2027
|
Fiscal Year: 2027
|
242000000
|
SPECIFICATIONS
|
Fiscal Year: 2027
|
Fiscal Year: 2027
|
228550000
|
SUBMIT UTILITY DATA
|
Fiscal Year: 2027
|
Fiscal Year: 2027
|
269000000
|
ALL UTILITIES CLEAR
|
Fiscal Year: 2027
|
Fiscal Year: 2027
|
266000000
|
UTILITIES CERTIFIED
|
Fiscal Year: 2027
|
Fiscal Year: 2027
|
222000000
|
ALL PERMITS CLEAR
|
Fiscal Year: 2027
|
Fiscal Year: 2027
|
235500000
|
SUBMIT PLANS FOR REVIEW
|
Fiscal Year: 2027
|
Fiscal Year: 2027
|
235530000
|
SUBMIT PLANS FOR REVIEW
|
Fiscal Year: 2027
|
Fiscal Year: 2028
|
212000000
|
TRANSMIT PKG FOR LETTING
|
Fiscal Year: 2027
|
Fiscal Year: 2027
|
278000000
|
ADVERTISMENT FOR LETTING
|
Fiscal Year: 2027
|
Fiscal Year: 2027
|
278220000
|
ADVERTISMENT FOR LETTING
|
Fiscal Year: 2027
|
Fiscal Year: 2028
|
280000000
|
LETTING DATE
|
Fiscal Year: 2028
|
Fiscal Year: 2028
|
203000000
|
C.E.I. CONS. CONT. EXEC.
|
Fiscal Year: 2028
|
Fiscal Year: 2028
|