FDOT OWPB - WP Reports; 5 Year Work Program Item Detail
Office of Work Program and Budget
Updated: 4/17/2026 12:42 AM

Five Year Work Program
Selection Criteria
 All in State 
 2026-2030 AD 
 Item Number:452154-1 




Scheduled Activities may or may not be confirmed dates and are subject to change without notice.
Please contact the Program Services Office at the appropriate District office for validation.
 
452154-1 I-75 AT JONES LOOP TRUCK PARKING
District 01 - Charlotte County
 
Project Manager: NEM-AEB-UVV
Type of Work: PARKING FACILITY
Activity Description Planned
Start
Planned
Finish
233000000 P.E. CONTRACT EXECUTED 04/04/2024 A 04/04/2024 A
106000000 DESIGN SURVEY 04/13/2024 A 07/01/2024 A
250000000 P.E. BEGIN 05/01/2024 A 05/01/2024 A
265020000 UTILITY PRE-DESIGN CONF 07/18/2024 A 07/18/2024 A
168120000 Q. A. REVIEW 08/01/2024 A 08/01/2024 A
109510000 DRAINAGE DESIGN 09/12/2024 A 09/12/2024 A
271440000 GEOTECH EVALUATION 10/01/2024 A 12/13/2024 A
271040000 GEOTECH EVALUATION 10/15/2024 A 11/15/2024 A
132120000 ROADWAY SOILS REPORT 01/03/2025 A 04/04/2025 A
264011330 UTILITY CONTACT 01/08/2025 A 01/08/2025 A
264040000 UTILITY CONTACT 01/08/2025 A 03/03/2025 A
132110000 ROADWAY SOILS REPORT 01/15/2025 A 01/15/2025 A
228130000 SUBMIT UTILITY DATA 01/15/2025 A 07/17/2025 A
132000000 ROADWAY SOILS REPORT 01/15/2025 A 08/28/2025 A
113200000 ROADWAY PLANS 01/15/2025 A 08/29/2025 A
197020000 PAVEMENT DESIGN 04/01/2025 A 08/25/2025 A
228009220 SUBMIT UTILITY DATA 05/27/2025 A 08/28/2025 A
228001070 SUBMIT UTILITY DATA 06/27/2025 A 08/28/2025 A
131000000 ROADWAY SOILS SURVEY 07/28/2025 A 08/27/2025 A
228001220 SUBMIT UTILITY DATA 07/28/2025 A 08/28/2025 A
102210000 TRAFFIC STUDIES 08/04/2025 A 08/04/2025 A
302100000 PHASE II PLANS REVIEW 08/29/2025 A 09/29/2025 A
113011270 ROADWAY PLANS 09/30/2025 A 10/13/2025 A
235240000 SUBMIT PLANS FOR REVIEW 11/17/2025 A 11/17/2025 A
228011450 SUBMIT UTILITY DATA 12/09/2025 A 12/09/2025 A
159300000 COLOR CODE UTILITY PLANS 12/09/2025 A 01/30/2026 A
264001550 UTILITY CONTACT 01/08/2026 A 01/08/2026 A
113300000 ROADWAY PLANS 01/08/2026 A 03/20/2026 A
272000000 FILE PERMITS 02/20/2026 A 02/20/2026 A
145020000 PERMITS 02/20/2026 A 04/14/2027 
113370000 ROADWAY PLANS 03/30/2026 A 07/07/2026 
264019800 UTILITY CONTACT 04/10/2026  05/15/2026 
145400000 PERMITS 04/10/2026  10/19/2026 
128070000 ASBESTOS SURVEY/ABATEMENT 04/10/2026  11/17/2026 
336310000 ENVIRONMENTAL REEVALUATION 04/10/2026  Fiscal Year: 2028
290220000 COMMUNITY AWARE PLAN COMPLETE 04/10/2026  Fiscal Year: 2028
290270000 COMMUNITY AWARE PLAN COMPLETE 04/10/2026  Fiscal Year: 2028
168140000 Q. A. REVIEW 04/10/2026  Fiscal Year: 2028
197100000 PAVEMENT DESIGN 04/10/2026  Fiscal Year: 2028
132440000 ROADWAY SOILS REPORT 04/10/2026  Fiscal Year: 2028
264011680 UTILITY CONTACT 04/13/2026  06/15/2026 
145450000 PERMITS 04/13/2026  04/14/2027 
290290000 COMMUNITY AWARE PLAN COMPLETE 05/08/2026  Fiscal Year: 2028
168190000 Q. A. REVIEW 05/08/2026  Fiscal Year: 2028
228009320 SUBMIT UTILITY DATA 05/11/2026  07/07/2026 
264011960 UTILITY CONTACT 05/11/2026  07/07/2026 
303100000 PHASE III PLANS REVIEW 05/26/2026  12/04/2026 
264013960 UTILITY CONTACT 06/02/2026  07/08/2026 
868670000 JPA PREPARED 06/03/2026  08/19/2026 
228400000 SUBMIT UTILITY DATA 06/03/2026  09/18/2026 
336330000 ENVIRONMENTAL REEVALUATION 06/10/2026  Fiscal Year: 2028
128090000 ASBESTOS SURVEY/ABATEMENT 06/22/2026  12/04/2026 
264019900 UTILITY CONTACT 07/16/2026  08/20/2026 
264012680 UTILITY CONTACT 07/17/2026  09/18/2026 
264019960 UTILITY CONTACT 08/14/2026  09/21/2026 
264012960 UTILITY CONTACT 08/17/2026  10/19/2026 
264011970 UTILITY CONTACT 09/15/2026  11/09/2026 
228001960 SUBMIT UTILITY DATA 10/06/2026  12/03/2026 
171000000 REQUEST CONTRACT TIME 10/27/2026  12/04/2026 
171200000 REQUEST CONTRACT TIME 10/28/2026  01/04/2027 
113400000 ROADWAY PLANS 10/28/2026  01/04/2027 
310100000 PHASE IV PLANS REVIEW 11/30/2026  01/19/2027 
255000000 R/W CERTIFIED 12/01/2026  04/15/2027 
113011470 ROADWAY PLANS 12/14/2026  03/17/2027 
336510000 ENVIRONMENTAL REEVALUATION 12/14/2026  03/18/2027 
264013970 UTILITY CONTACT 12/14/2026  03/30/2027 
163050000 MAINT OR FUNDS AGREEMENT 12/14/2026  04/15/2027 
228400010 SUBMIT UTILITY DATA 12/15/2026  04/13/2027 
113500000 ROADWAY PLANS 12/15/2026  04/14/2027 
336530000 ENVIRONMENTAL REEVALUATION 12/21/2026  04/15/2027 
269000000 ALL UTILITIES CLEAR 12/30/2026  04/14/2027 
266000000 UTILITIES CERTIFIED 12/31/2026  04/15/2027 
235500000 SUBMIT PLANS FOR REVIEW 01/13/2027  04/15/2027 
235530000 SUBMIT PLANS FOR REVIEW 01/13/2027  Fiscal Year: 2028
279000000 RAILROAD CLEAR 02/05/2027  02/05/2027 
226000000 PLANS TO DIST SPECS 04/19/2027  04/19/2027 
242000000 SPECIFICATIONS 04/19/2027  05/31/2027 
222000000 ALL PERMITS CLEAR 04/23/2027  04/23/2027 
278000000 ADVERTISMENT FOR LETTING 06/28/2027  06/28/2027 
278220000 ADVERTISMENT FOR LETTING 06/28/2027  Fiscal Year: 2028