Activity
|
Description
|
Planned
Start
|
Planned
Finish
|
250010000
|
P.E. BEGIN
|
10/28/2022 A
|
10/28/2022 A
|
450032000
|
TIP / STIP AMENDMENT
|
10/28/2022 A
|
11/28/2022 A
|
164032000
|
PREPARE SCOPE OF WORK
|
10/28/2022 A
|
02/20/2023 A
|
256010000
|
ORDER DESIGN TRAFFIC
|
11/17/2022 A
|
12/27/2022 A
|
153010000
|
PAVEMENT SURVEY
|
12/05/2022 A
|
12/08/2022 A
|
237032000
|
FHWA AUTHORITY RECEIVED
|
02/14/2023 A
|
02/14/2023 A
|
299032000
|
REQUEST FOR AUTHORIZATION
|
02/15/2023 A
|
02/15/2023 A
|
234032000
|
NOTICE TO PROCEED
|
03/01/2023 A
|
03/01/2023 A
|
233032000
|
P.E. CONTRACT EXECUTED
|
03/01/2023 A
|
03/01/2023 A
|
106010000
|
DESIGN SURVEY
|
03/03/2023 A
|
05/12/2023 A
|
132010000
|
ROADWAY SOILS REPORT
|
03/15/2023 A
|
06/09/2023 A
|
247010000
|
LOCAL GOVERNMENT AGREEMENT
|
03/30/2023 A
|
03/30/2023 A
|
197010000
|
PAVEMENT DESIGN
|
03/31/2023 A
|
04/24/2023 A
|
260010000
|
TYPICAL SECTION APPROVED
|
04/03/2023 A
|
06/22/2023 A
|
290010000
|
COMMUNITY AWARE PLAN COMPLETE
|
04/05/2023 A
|
04/05/2023 A
|
382000000
|
PREPARE PHII (60%) DESIGN PLN
|
04/28/2023 A
|
08/24/2023 A
|
405010000
|
CEI CONSULTANT ADVERTISE
|
05/15/2023 A
|
05/15/2023 A
|
406010000
|
CEI CONSULT SHORTLISTING
|
06/12/2023 A
|
06/12/2023 A
|
106020000
|
DESIGN SURVEY
|
06/29/2023 A
|
07/12/2023 A
|
132020000
|
ROADWAY SOILS REPORT
|
06/30/2023 A
|
07/28/2023 A
|
228010000
|
SUBMIT UTILITY DATA
|
07/06/2023 A
|
07/06/2023 A
|
407010000
|
CEI CONSULT FINAL SELECTION
|
07/10/2023 A
|
07/10/2023 A
|
749000000
|
TYPE 1 CE APPROVAL
|
07/28/2023 A
|
01/30/2024 A
|
272010000
|
FILE PERMITS
|
08/02/2023 A
|
08/02/2023 A
|
137010000
|
IN-HOUSE R/W LICENSE AGREEMNT
|
08/25/2023 A
|
08/25/2023 A
|
182010000
|
REQUEST BRIDGE NUMBER
|
08/28/2023 A
|
08/28/2023 A
|
182020000
|
REQUEST BRIDGE NUMBER
|
08/28/2023 A
|
08/28/2023 A
|
302010000
|
PHASE II PLANS REVIEW
|
08/28/2023 A
|
09/18/2023 A
|
333032000
|
CULTURAL RESOURCES ASSESS SURV
|
08/28/2023 A
|
11/15/2023 A
|
297060000
|
CONST. ESTIMATE UPDATE
|
09/14/2023 A
|
09/14/2023 A
|
384000000
|
PREPARE PHIV (100%) DESIGN PLN
|
09/18/2023 A
|
11/30/2023 A
|
348010000
|
PARTNERSHIP MEETING
|
09/19/2023 A
|
09/19/2023 A
|
272020000
|
FILE PERMITS
|
10/06/2023 A
|
10/06/2023 A
|
145010000
|
PERMITS
|
10/10/2023 A
|
02/29/2024 A
|
450052000
|
TIP / STIP AMENDMENT
|
10/25/2023 A
|
10/25/2023 A
|
310010000
|
PHASE IV PLANS REVIEW
|
12/04/2023 A
|
12/29/2023 A
|
187010000
|
NO R/W REQRD CERTIFICATION
|
12/12/2023 A
|
12/12/2023 A
|
297100000
|
CONST. ESTIMATE UPDATE
|
12/22/2023 A
|
12/22/2023 A
|
113070000
|
ROADWAY PLANS
|
12/29/2023 A
|
01/17/2024 A
|
130010000
|
SOIL CROSS SECTION
|
12/29/2023 A
|
01/26/2024 A
|
163010000
|
MAINT OR FUNDS AGREEMENT
|
01/03/2024 A
|
01/03/2024 A
|
264010000
|
UTILITY CONTACT
|
01/18/2024 A
|
01/18/2024 A
|
265010000
|
UTILITY PRE-DESIGN CONF
|
01/18/2024 A
|
01/18/2024 A
|
172010000
|
CHECK LIST ACTIVITIES
|
01/26/2024 A
|
01/26/2024 A
|
248010000
|
D.M.S APPROVAL
|
01/26/2024 A
|
01/26/2024 A
|
204010000
|
PRODUCTION DATE
|
01/26/2024 A
|
01/26/2024 A
|
126010000
|
UTILITY RELOCATION
|
01/26/2024 A
|
03/11/2024 A
|
226010000
|
PLANS TO DIST SPECS
|
01/29/2024 A
|
01/29/2024 A
|
242010000
|
SPECIFICATIONS
|
01/29/2024 A
|
02/16/2024 A
|
376010000
|
ENVIRONMENTAL CLEAR/CERTIF
|
01/30/2024 A
|
01/30/2024 A
|
279010000
|
RAILROAD CLEAR
|
01/30/2024 A
|
01/30/2024 A
|
205010000
|
CNST UTILITY CONTRACT EXECUTED
|
02/12/2024 A
|
02/12/2024 A
|
171010000
|
REQUEST CONTRACT TIME
|
02/22/2024 A
|
02/22/2024 A
|
242020000
|
SPECIFICATIONS
|
03/04/2024 A
|
03/15/2024 A
|
222010000
|
ALL PERMITS CLEAR
|
03/08/2024 A
|
03/08/2024 A
|
266010000
|
UTILITIES CERTIFIED
|
03/11/2024 A
|
03/11/2024 A
|
242030000
|
SPECIFICATIONS
|
04/01/2024 A
|
04/05/2024 A
|
297040000
|
CONST. ESTIMATE UPDATE
|
04/02/2024 A
|
04/02/2024 A
|
237052000
|
FHWA AUTHORITY RECEIVED
|
04/08/2024 A
|
04/16/2024 A
|
212010000
|
TRANSMIT PKG FOR LETTING
|
04/16/2024 A
|
04/16/2024 A
|
408010000
|
CEI ENCUMBERED
|
06/03/2024
|
06/03/2024
|
203010000
|
C.E.I. CONS. CONT. EXEC.
|
06/10/2024
|
06/10/2024
|
280SET000
|
LETTING DATE
|
06/12/2024
|
06/12/2024
|