Five Year Work Program
Selection Criteria
 All in State 
 2025-2029 AD 
 Item Number:210711-5 




Scheduled Activities may or may not be confirmed dates and are subject to change without notice.
Please contact the Program Services Office at the appropriate District office for validation.
 
210711-5 SRA1A(SR200) FROM ONEIL SCOTT ROAD TO AMELIA RIVER
District 02 - Nassau County
 
Project Manager: KT/VM/CR/JH
Type of Work: RESURFACING
Activity Description Planned
Start
Planned
Finish
304020000 CORING 09/26/2022 A 09/26/2022 A
281010000 SUBMIT RR DATA 11/08/2022 A 11/08/2022 A
304010000 CORING 02/07/2023 A 02/07/2023 A
155010000 UPDATE SCOPE OF WORK 03/01/2023 A 03/24/2023 A
229010000 ADVERTISE DISTRICT CONTRACT 03/27/2023 A 04/10/2023 A
232010000 DESIGN CONSULTANT ADVERTISE 03/27/2023 A 07/24/2023 A
233010000 P.E. CONTRACT EXECUTED 07/24/2023 A 07/24/2023 A
254010000 ORDER AERIALS 08/18/2023 A 08/18/2023 A
106010000 DESIGN SURVEY 08/21/2023 A 02/12/2024 A
234320100 NOTICE TO PROCEED 10/11/2023 A 10/11/2023 A
164010000 PREPARE SCOPE OF WORK 10/27/2023 A 12/22/2023 A
199010000 PLANS SUBMIT TO DIST ESTIMATES 12/04/2023 A 12/28/2023 A
264010000 UTILITY CONTACT 12/22/2023 A 12/22/2023 A
164020000 PREPARE SCOPE OF WORK 12/22/2023 A 02/13/2024 A
113040000 ROADWAY PLANS 12/22/2023 A 04/04/2024 A
264080000 UTILITY CONTACT 01/09/2024 A 03/07/2024 A
271010000 GEOTECH EVALUATION 02/05/2024 A 02/05/2024 A
264050000 UTILITY CONTACT 02/16/2024 A 02/16/2024 A
108010000 PLOT DESIGN SURVEY 02/19/2024 A 02/19/2024 A
264040000 UTILITY CONTACT 02/19/2024 A 02/19/2024 A
169010000 PRELIM. FIELD REVIEW 03/27/2024 A 03/27/2024 A
199070000 PLANS SUBMIT TO DIST ESTIMATES 04/04/2024 A 04/04/2024 A
164030000 PREPARE SCOPE OF WORK 04/04/2024 A 04/04/2024 A
264090000 UTILITY CONTACT 04/04/2024 A 04/04/2024 A
199080000 PLANS SUBMIT TO DIST ESTIMATES 04/04/2024 A 04/08/2024 A
310010000 PHASE IV PLANS REVIEW 04/04/2024 A 05/02/2024 A
163010000 MAINT OR FUNDS AGREEMENT 04/05/2024 A 04/05/2024 A
445030000 OWNERSHIP AGREEMENT 04/05/2024 A 04/05/2024 A
245010000 FINAL BID ABILITY 04/09/2024 A 04/09/2024 A
376010000 ENVIRONMENTAL CLEAR/CERTIF 04/22/2024 A 04/22/2024 A
187010000 NO R/W REQRD CERTIFICATION 04/22/2024 A 04/22/2024 A
264110000 UTILITY CONTACT 04/23/2024 A 05/15/2024 A
310040000 PHASE IV PLANS REVIEW 05/06/2024 A 05/24/2024 A
264100000 UTILITY CONTACT 05/15/2024 A 05/16/2024 A
266010000 UTILITIES CERTIFIED 05/20/2024 A 05/20/2024 A
171010000 REQUEST CONTRACT TIME 06/13/2024 A 06/13/2024 A
222020000 ALL PERMITS CLEAR 06/17/2024 A 06/17/2024 A
226010000 PLANS TO DIST SPECS 07/08/2024  07/08/2024 
188000000 PRELIMINARY REVIEW 07/08/2024  07/08/2024 
250020000 P.E. BEGIN 07/08/2024  05/23/2025 
204010000 PRODUCTION DATE 07/09/2024  07/09/2024 
242030000 SPECIFICATIONS 07/09/2024  07/12/2024 
212010000 TRANSMIT PKG FOR LETTING 07/15/2024  07/15/2024 
280010000 LETTING DATE 09/25/2024  09/25/2024 
330010000 CEI BEGIN 09/26/2024  11/22/2024 
312010000 CONSTRUCTION 11/25/2024  05/23/2025 
203010000 C.E.I. CONS. CONT. EXEC. 11/27/2024  11/27/2024 
203020000 C.E.I. CONS. CONT. EXEC. 11/27/2024  11/27/2024