EMERGENCY INFORMATION FDOT Emergency Travel Alert: For information on the current situation, please visit the following page - Alerts.


State of Florida Department of Transportation logo
Florida Department of

TRANSPORTATION

FDOT OWPB - WP Reports; 5 Year Work Program Item Detail
Office of Work Program and Budget
Updated: 4/9/2025 9:15 PM

Five Year Work Program
Selection Criteria
 All in State 
 2025-2030 G1 
 Item Number:219484-2 




Scheduled Activities may or may not be confirmed dates and are subject to change without notice.
Please contact the Program Services Office at the appropriate District office for validation.
 
219484-2 SR 61 (US 319) CRAWFORDVILLE RD FR S OF SR 61 SB TO ARDEN RD
District 03 - Leon County
 
Project Manager: AMY HEIKKINEN
Type of Work: RESURFACING
Activity Description Planned
Start
Planned
Finish
164032000 PREPARE SCOPE OF WORK 04/19/2022 A 06/06/2022 A
256010000 ORDER DESIGN TRAFFIC 05/09/2022 A 05/13/2022 A
153010000 PAVEMENT SURVEY 06/07/2022 A 07/20/2022 A
232032000 DESIGN CONSULTANT ADVERTISE 06/13/2022 A 06/13/2022 A
450032000 TIP / STIP AMENDMENT 06/20/2022 A 06/20/2022 A
401032000 CONSULT SHORTLISTING 07/11/2022 A 07/11/2022 A
250010000 P.E. BEGIN 07/29/2022 A 07/29/2022 A
197010000 PAVEMENT DESIGN 08/22/2022 A 09/06/2022 A
402032000 CONSULT FINAL SELECTION 08/23/2022 A 08/23/2022 A
237032000 FHWA AUTHORITY RECEIVED 10/14/2022 A 10/14/2022 A
299032000 REQUEST FOR AUTHORIZATION 10/24/2022 A 10/24/2022 A
233032000 P.E. CONTRACT EXECUTED 10/31/2022 A 10/31/2022 A
234032000 NOTICE TO PROCEED 11/14/2022 A 11/14/2022 A
106010000 DESIGN SURVEY 11/23/2022 A 03/01/2023 A
228010000 SUBMIT UTILITY DATA 11/28/2022 A 11/28/2022 A
290010000 COMMUNITY AWARE PLAN COMPLETE 12/19/2022 A 12/19/2022 A
260010000 TYPICAL SECTION APPROVED 12/27/2022 A 05/12/2023 A
381000000 PREPARE PHI (30%) DESIGN PLN 03/01/2023 A 06/09/2023 A
106020000 DESIGN SURVEY 03/31/2023 A 06/06/2023 A
297020000 CONST. ESTIMATE UPDATE 04/28/2023 A 04/28/2023 A
294010000 PROCESS EXCEPTIONS/VARIANCE 05/19/2023 A 08/03/2023 A
132010000 ROADWAY SOILS REPORT 05/26/2023 A 05/30/2023 A
301010000 PHASE I PLANS REVIEW 06/12/2023 A 06/28/2023 A
297030000 CONST. ESTIMATE UPDATE 06/14/2023 A 06/14/2023 A
297010000 CONST. ESTIMATE UPDATE 06/20/2023 A 06/20/2023 A
132020000 ROADWAY SOILS REPORT 06/29/2023 A 09/20/2023 A
382000000 PREPARE PHII (60%) DESIGN PLN 06/29/2023 A 11/22/2023 A
264010000 UTILITY CONTACT 07/05/2023 A 07/05/2023 A
333032000 CULTURAL RESOURCES ASSESS SURV 11/21/2023 A 05/07/2024 A
302010000 PHASE II PLANS REVIEW 11/22/2023 A 12/12/2023 A
297060000 CONST. ESTIMATE UPDATE 12/08/2023 A 12/08/2023 A
383000000 PREPARE PHIII (90%) DESIGN PLN 12/12/2023 A 03/27/2024 A
272010000 FILE PERMITS 12/21/2023 A 12/21/2023 A
272020000 FILE PERMITS 12/21/2023 A 12/21/2023 A
749000000 TYPE 1 CE APPROVAL 12/29/2023 A 05/31/2024 A
145010000 PERMITS 02/20/2024 A 02/23/2024 A
182010000 REQUEST BRIDGE NUMBER 02/28/2024 A 02/28/2024 A
182020000 REQUEST BRIDGE NUMBER 02/28/2024 A 02/28/2024 A
292010000 PUBLIC INFO MEETING 03/27/2024 A 03/27/2024 A
297090000 CONST. ESTIMATE UPDATE 03/29/2024 A 03/29/2024 A
303010000 PHASE III PLANS REVIEW 03/29/2024 A 04/12/2024 A
348010000 PARTNERSHIP MEETING 04/10/2024 A 04/10/2024 A
384000000 PREPARE PHIV (100%) DESIGN PLN 04/15/2024 A 06/19/2024 A
126010000 UTILITY RELOCATION 05/14/2024 A 10/04/2024 A
265010000 UTILITY PRE-DESIGN CONF 06/03/2024 A 06/03/2024 A
310010000 PHASE IV PLANS REVIEW 06/19/2024 A 07/05/2024 A
297100000 CONST. ESTIMATE UPDATE 06/28/2024 A 06/28/2024 A
137010000 IN-HOUSE R/W LICENSE AGREEMNT 06/28/2024 A 06/28/2024 A
130010000 SOIL CROSS SECTION 06/28/2024 A 07/02/2024 A
113070000 ROADWAY PLANS 07/08/2024 A 08/09/2024 A
266010000 UTILITIES CERTIFIED 10/17/2024 A 10/17/2024 A
172010000 CHECK LIST ACTIVITIES 11/01/2024 A 11/01/2024 A
171010000 REQUEST CONTRACT TIME 12/11/2024 A 12/11/2024 A
187010000 NO R/W REQRD CERTIFICATION 12/12/2024 A 12/12/2024 A
279010000 RAILROAD CLEAR 12/13/2024 A 12/13/2024 A
450052000 TIP / STIP AMENDMENT 12/20/2024 A 12/20/2024 A
748000000 ENV DOC REEVAL-CONST ADVERTSMT 12/27/2024 A 02/18/2025 A
163010000 MAINT OR FUNDS AGREEMENT 01/02/2025 A 01/02/2025 A
247010000 LOCAL GOVERNMENT AGREEMENT 01/31/2025 A 01/31/2025 A
376010000 ENVIRONMENTAL CLEAR/CERTIF 02/19/2025 A 02/19/2025 A
222010000 ALL PERMITS CLEAR 03/10/2025 A 03/10/2025 A
248010000 D.M.S APPROVAL 03/10/2025 A 03/10/2025 A
204010000 PRODUCTION DATE 03/14/2025 A 03/14/2025 A
226010000 PLANS TO DIST SPECS 03/17/2025 A 03/17/2025 A
242010000 SPECIFICATIONS 03/17/2025 A 04/04/2025 A
242020000 SPECIFICATIONS 04/21/2025 A 05/09/2025 A
297040000 CONST. ESTIMATE UPDATE 05/14/2025 A 05/14/2025 A
237052000 FHWA AUTHORITY RECEIVED 05/22/2025 A 06/04/2025 A
212010000 TRANSMIT PKG FOR LETTING 05/23/2025 A 05/23/2025 A
405010000 CEI CONSULTANT ADVERTISE 05/27/2025 A 05/27/2025 A
406010000 CEI CONSULT SHORTLISTING 06/16/2025 A 06/16/2025 A
407010000 CEI CONSULT FINAL SELECTION 06/30/2025  06/30/2025 
280SET000 LETTING DATE 07/30/2025  07/30/2025 
193520000 LOCAL FUNDS DEPOSITED 07/31/2025  08/18/2025 
205010000 CNST UTILITY CONTRACT EXECUTED 08/01/2025  08/18/2025 
408010000 CEI ENCUMBERED 08/11/2025  08/11/2025 
203010000 C.E.I. CONS. CONT. EXEC. 08/18/2025  08/18/2025