 Item Number:219485-2 




Scheduled Activities may or may not be confirmed dates and are subject to change without notice.
Please contact the Program Services Office at the appropriate District office for validation.
 
219485-2 SR 366 PENSACOLA ST FROM RAILROAD OVERPASS TO SR 366 STADIUM DR
District 03 - Leon County
 
Project Manager: JORDAN BURNETT
Type of Work: RESURFACING
Activity Description Planned
Start
Planned
Finish
450032000 TIP / STIP AMENDMENT 03/15/2022 A 03/15/2022 A
164032000 PREPARE SCOPE OF WORK 03/28/2022 A 06/20/2022 A
256010000 ORDER DESIGN TRAFFIC 04/07/2022 A 04/19/2022 A
250010000 P.E. BEGIN 07/01/2022 A 07/01/2022 A
237032000 FHWA AUTHORITY RECEIVED 07/08/2022 A 07/08/2022 A
299032000 REQUEST FOR AUTHORIZATION 07/13/2022 A 07/13/2022 A
228010000 SUBMIT UTILITY DATA 07/19/2022 A 07/19/2022 A
233032000 P.E. CONTRACT EXECUTED 07/22/2022 A 07/22/2022 A
234032000 NOTICE TO PROCEED 07/29/2022 A 07/29/2022 A
106010000 DESIGN SURVEY 08/22/2022 A 02/10/2023 A
132010000 ROADWAY SOILS REPORT 08/26/2022 A 08/26/2022 A
290010000 COMMUNITY AWARE PLAN COMPLETE 09/08/2022 A 09/08/2022 A
153010000 PAVEMENT SURVEY 09/26/2022 A 03/07/2023 A
260010000 TYPICAL SECTION APPROVED 02/13/2023 A 03/09/2023 A
381000000 PREPARE PHI (30%) DESIGN PLN 02/13/2023 A 05/02/2023 A
197010000 PAVEMENT DESIGN 03/01/2023 A 03/15/2023 A
294010000 PROCESS EXCEPTIONS/VARIANCE 03/13/2023 A 04/03/2023 A
106020000 DESIGN SURVEY 04/04/2023 A 04/11/2023 A
301010000 PHASE I PLANS REVIEW 05/02/2023 A 05/26/2023 A
264010000 UTILITY CONTACT 05/17/2023 A 05/17/2023 A
247010000 LOCAL GOVERNMENT AGREEMENT 05/23/2023 A 07/28/2023 A
382000000 PREPARE PHII (60%) DESIGN PLN 05/23/2023 A 08/29/2023 A
297010000 CONST. ESTIMATE UPDATE 05/24/2023 A 05/24/2023 A
297020000 CONST. ESTIMATE UPDATE 05/24/2023 A 05/24/2023 A
297030000 CONST. ESTIMATE UPDATE 05/25/2023 A 05/25/2023 A
132020000 ROADWAY SOILS REPORT 05/26/2023 A 05/26/2023 A
272010000 FILE PERMITS 08/29/2023 A 08/29/2023 A
137010000 IN-HOUSE R/W LICENSE AGREEMNT 08/29/2023 A 08/29/2023 A
302010000 PHASE II PLANS REVIEW 08/30/2023 A 09/22/2023 A
749000000 TYPE 1 CE APPROVAL 08/30/2023 A 03/20/2024 A
333032000 CULTURAL RESOURCES ASSESS SURV 08/31/2023 A 12/15/2023 A
297060000 CONST. ESTIMATE UPDATE 09/14/2023 A 09/14/2023 A
383000000 PREPARE PHIII (90%) DESIGN PLN 09/22/2023 A 12/11/2023 A
348010000 PARTNERSHIP MEETING 09/29/2023 A 09/29/2023 A
292010000 PUBLIC INFO MEETING 10/18/2023 A 10/18/2023 A
182010000 REQUEST BRIDGE NUMBER 12/11/2023 A 12/11/2023 A
182020000 REQUEST BRIDGE NUMBER 12/12/2023 A 12/12/2023 A
303010000 PHASE III PLANS REVIEW 12/13/2023 A 01/19/2024 A
384000000 PREPARE PHIV (100%) DESIGN PLN 12/28/2023 A 02/29/2024 A
297090000 CONST. ESTIMATE UPDATE 01/03/2024 A 01/03/2024 A
272020000 FILE PERMITS 01/23/2024 A 01/23/2024 A
310010000 PHASE IV PLANS REVIEW 03/08/2024 A 03/29/2024 A
145010000 PERMITS 03/12/2024 A 04/04/2024 A
265010000 UTILITY PRE-DESIGN CONF 03/19/2024 A 03/19/2024 A
126010000 UTILITY RELOCATION 03/20/2024 A 06/18/2024 
113070000 ROADWAY PLANS 03/22/2024 A 05/31/2024 
297100000 CONST. ESTIMATE UPDATE 03/29/2024 A 03/29/2024 A
130010000 SOIL CROSS SECTION 03/29/2024 A 03/29/2024 A
163010000 MAINT OR FUNDS AGREEMENT 04/01/2024 A 04/01/2024 A
222010000 ALL PERMITS CLEAR 04/26/2024  06/24/2024 
376010000 ENVIRONMENTAL CLEAR/CERTIF 04/26/2024  06/24/2024 
450052000 TIP / STIP AMENDMENT 04/26/2024  06/24/2024 
266010000 UTILITIES CERTIFIED 05/14/2024  06/19/2024 
171010000 REQUEST CONTRACT TIME 05/15/2024  06/24/2024 
172010000 CHECK LIST ACTIVITIES 06/03/2024  06/21/2024 
187010000 NO R/W REQRD CERTIFICATION 06/04/2024  06/24/2024 
279010000 RAILROAD CLEAR 06/04/2024  06/24/2024 
248010000 D.M.S APPROVAL 06/24/2024  06/24/2024 
204010000 PRODUCTION DATE 06/28/2024  06/28/2024 
405010000 CEI CONSULTANT ADVERTISE 07/01/2024  07/01/2024 
226010000 PLANS TO DIST SPECS 07/01/2024  07/01/2024 
242010000 SPECIFICATIONS 07/01/2024  07/19/2024 
205010000 CNST UTILITY CONTRACT EXECUTED 07/01/2024  09/05/2024 
822010000 JPA EXECUTED 07/01/2024  09/05/2024 
406010000 CEI CONSULT SHORTLISTING 07/29/2024  07/29/2024 
242020000 SPECIFICATIONS 08/05/2024  08/16/2024 
297040000 CONST. ESTIMATE UPDATE 09/02/2024  09/06/2024 
242030000 SPECIFICATIONS 09/02/2024  09/06/2024 
212010000 TRANSMIT PKG FOR LETTING 09/06/2024  09/06/2024 
237052000 FHWA AUTHORITY RECEIVED 09/12/2024  10/07/2024 
407010000 CEI CONSULT FINAL SELECTION 09/16/2024  09/16/2024 
408010000 CEI ENCUMBERED 11/11/2024  11/11/2024 
280TBD000 LETTING DATE 11/13/2024  11/13/2024 
203010000 C.E.I. CONS. CONT. EXEC. 11/18/2024  11/18/2024