Activity
|
Description
|
Planned
Start
|
Planned
Finish
|
164032000
|
PREPARE SCOPE OF WORK
|
01/10/2022 A
|
02/02/2022 A
|
256010000
|
ORDER DESIGN TRAFFIC
|
01/18/2022 A
|
02/03/2022 A
|
153010000
|
PAVEMENT SURVEY
|
02/01/2022 A
|
03/29/2022 A
|
232032000
|
DESIGN CONSULTANT ADVERTISE
|
02/07/2022 A
|
02/07/2022 A
|
450032000
|
TIP / STIP AMENDMENT
|
02/11/2022 A
|
02/11/2022 A
|
401032000
|
CONSULT SHORTLISTING
|
02/28/2022 A
|
02/28/2022 A
|
402032000
|
CONSULT FINAL SELECTION
|
04/18/2022 A
|
04/18/2022 A
|
250010000
|
P.E. BEGIN
|
07/01/2022 A
|
07/01/2022 A
|
237032000
|
FHWA AUTHORITY RECEIVED
|
07/08/2022 A
|
07/08/2022 A
|
299032000
|
REQUEST FOR AUTHORIZATION
|
07/12/2022 A
|
07/12/2022 A
|
234032000
|
NOTICE TO PROCEED
|
07/27/2022 A
|
07/27/2022 A
|
233032000
|
P.E. CONTRACT EXECUTED
|
07/28/2022 A
|
07/28/2022 A
|
106010000
|
DESIGN SURVEY
|
07/29/2022 A
|
10/20/2022 A
|
290010000
|
COMMUNITY AWARE PLAN COMPLETE
|
08/12/2022 A
|
08/12/2022 A
|
228010000
|
SUBMIT UTILITY DATA
|
08/19/2022 A
|
08/19/2022 A
|
197010000
|
PAVEMENT DESIGN
|
08/26/2022 A
|
09/20/2022 A
|
381000000
|
PREPARE PHI (30%) DESIGN PLN
|
10/21/2022 A
|
03/20/2023 A
|
132010000
|
ROADWAY SOILS REPORT
|
10/28/2022 A
|
10/28/2022 A
|
106020000
|
DESIGN SURVEY
|
11/28/2022 A
|
12/01/2022 A
|
260010000
|
TYPICAL SECTION APPROVED
|
11/28/2022 A
|
12/07/2022 A
|
294010000
|
PROCESS EXCEPTIONS/VARIANCE
|
02/06/2023 A
|
03/20/2023 A
|
132020000
|
ROADWAY SOILS REPORT
|
03/29/2023 A
|
03/29/2023 A
|
301010000
|
PHASE I PLANS REVIEW
|
04/04/2023 A
|
05/04/2023 A
|
264010000
|
UTILITY CONTACT
|
04/17/2023 A
|
04/17/2023 A
|
297030000
|
CONST. ESTIMATE UPDATE
|
05/02/2023 A
|
05/02/2023 A
|
247010000
|
LOCAL GOVERNMENT AGREEMENT
|
05/05/2023 A
|
10/04/2024
|
297010000
|
CONST. ESTIMATE UPDATE
|
05/23/2023 A
|
05/23/2023 A
|
297020000
|
CONST. ESTIMATE UPDATE
|
05/23/2023 A
|
05/23/2023 A
|
382000000
|
PREPARE PHII (60%) DESIGN PLN
|
12/11/2023 A
|
03/29/2024 A
|
302010000
|
PHASE II PLANS REVIEW
|
04/01/2024 A
|
04/19/2024 A
|
333032000
|
CULTURAL RESOURCES ASSESS SURV
|
04/02/2024 A
|
09/16/2024 A
|
355010000
|
NMSA (NON MAJOR STATE ACTION)
|
04/02/2024 A
|
09/24/2024 A
|
383000000
|
PREPARE PHIII (90%) DESIGN PLN
|
04/19/2024 A
|
07/17/2024 A
|
297060000
|
CONST. ESTIMATE UPDATE
|
04/24/2024 A
|
04/24/2024 A
|
137010000
|
IN-HOUSE R/W LICENSE AGREEMNT
|
05/15/2024 A
|
06/28/2024 A
|
292010000
|
PUBLIC INFO MEETING
|
05/22/2024 A
|
05/22/2024 A
|
272010000
|
FILE PERMITS
|
06/04/2024 A
|
06/04/2024 A
|
298010000
|
R/W ESTIMATE UPDATE
|
06/18/2024 A
|
06/18/2024 A
|
348010000
|
PARTNERSHIP MEETING
|
06/27/2024 A
|
06/27/2024 A
|
450052000
|
TIP / STIP AMENDMENT
|
06/27/2024 A
|
06/27/2024 A
|
298060000
|
R/W ESTIMATE UPDATE
|
06/28/2024 A
|
07/18/2024 A
|
138010000
|
R/W PRELIMINARY MAP
|
07/11/2024 A
|
07/17/2024 A
|
142010000
|
SUBMIT PRE R/W REQUIREMENTS
|
07/17/2024 A
|
07/17/2024 A
|
210010000
|
REVIEW PRELIM R/W REQUIREMENTS
|
07/17/2024 A
|
07/22/2024 A
|
210020000
|
REVIEW PRELIM R/W REQUIREMENTS
|
07/17/2024 A
|
07/23/2024 A
|
210030000
|
REVIEW PRELIM R/W REQUIREMENTS
|
07/17/2024 A
|
07/26/2024 A
|
182010000
|
REQUEST BRIDGE NUMBER
|
07/18/2024 A
|
07/18/2024 A
|
182020000
|
REQUEST BRIDGE NUMBER
|
07/19/2024 A
|
07/19/2024 A
|
272020000
|
FILE PERMITS
|
07/23/2024 A
|
07/23/2024 A
|
163010000
|
MAINT OR FUNDS AGREEMENT
|
07/31/2024 A
|
07/31/2024 A
|
303010000
|
PHASE III PLANS REVIEW
|
08/06/2024 A
|
08/27/2024 A
|
193520000
|
LOCAL FUNDS DEPOSITED
|
08/12/2024 A
|
12/18/2024
|
297090000
|
CONST. ESTIMATE UPDATE
|
08/22/2024 A
|
08/22/2024 A
|
384000000
|
PREPARE PHIV (100%) DESIGN PLN
|
08/23/2024 A
|
09/17/2024
|
405010000
|
CEI CONSULTANT ADVERTISE
|
09/09/2024 A
|
09/09/2024 A
|
145010000
|
PERMITS
|
09/17/2024 A
|
09/19/2024 A
|
187010000
|
NO R/W REQRD CERTIFICATION
|
09/19/2024 A
|
09/19/2024 A
|
376010000
|
ENVIRONMENTAL CLEAR/CERTIF
|
09/24/2024 A
|
09/24/2024 A
|
172010000
|
CHECK LIST ACTIVITIES
|
09/27/2024
|
09/27/2024
|
323C20000
|
RETENTION/MITIGAT R/W REQRMTS
|
09/27/2024
|
02/12/2025
|
222010000
|
ALL PERMITS CLEAR
|
09/30/2024 A
|
09/30/2024 A
|
279010000
|
RAILROAD CLEAR
|
09/30/2024
|
10/07/2024
|
406010000
|
CEI CONSULT SHORTLISTING
|
10/07/2024
|
10/07/2024
|
248010000
|
D.M.S APPROVAL
|
10/07/2024
|
10/07/2024
|
137020000
|
IN-HOUSE R/W LICENSE AGREEMNT
|
10/07/2024
|
10/07/2024
|
265010000
|
UTILITY PRE-DESIGN CONF
|
10/09/2024
|
10/09/2024
|
126010000
|
UTILITY RELOCATION
|
10/10/2024
|
11/29/2024
|
204010000
|
PRODUCTION DATE
|
10/11/2024
|
10/11/2024
|
130010000
|
SOIL CROSS SECTION
|
10/11/2024
|
10/31/2024
|
226010000
|
PLANS TO DIST SPECS
|
10/14/2024
|
10/14/2024
|
297100000
|
CONST. ESTIMATE UPDATE
|
10/14/2024
|
10/18/2024
|
310010000
|
PHASE IV PLANS REVIEW
|
10/14/2024
|
11/01/2024
|
242010000
|
SPECIFICATIONS
|
10/14/2024
|
11/01/2024
|
407010000
|
CEI CONSULT FINAL SELECTION
|
10/21/2024
|
10/21/2024
|
113070000
|
ROADWAY PLANS
|
11/01/2024
|
11/01/2024
|
242020000
|
SPECIFICATIONS
|
11/18/2024
|
11/29/2024
|
408010000
|
CEI ENCUMBERED
|
12/02/2024
|
12/02/2024
|
266010000
|
UTILITIES CERTIFIED
|
12/02/2024
|
12/02/2024
|
205010000
|
CNST UTILITY CONTRACT EXECUTED
|
12/02/2024
|
12/19/2024
|
193620000
|
LOCAL FUNDS DEPOSITED
|
12/02/2024
|
12/19/2024
|
171010000
|
REQUEST CONTRACT TIME
|
12/03/2024
|
12/05/2024
|
203010000
|
C.E.I. CONS. CONT. EXEC.
|
12/09/2024
|
12/09/2024
|
297040000
|
CONST. ESTIMATE UPDATE
|
12/16/2024
|
12/20/2024
|
242030000
|
SPECIFICATIONS
|
12/16/2024
|
12/20/2024
|
370010000
|
PLANS TO DIST CONTRACT
|
12/20/2024
|
12/20/2024
|
229070000
|
ADVERTISE DISTRICT CONTRACT
|
12/23/2024
|
02/13/2025
|
280SET000
|
LETTING DATE
|
02/13/2025
|
02/13/2025
|