 Item Number:219668-2 




Scheduled Activities may or may not be confirmed dates and are subject to change without notice.
Please contact the Program Services Office at the appropriate District office for validation.
 
219668-2 SR 61 THOMASVILLE HWY FR N OF SR 63 (US 27) MONROE ST TO N OF 9TH AVE
District 03 - Leon County
 
Project Manager: TRAVIS JUSTICE
Type of Work: RESURFACING
Activity Description Planned
Start
Planned
Finish
164032000 PREPARE SCOPE OF WORK 01/10/2022 A 02/02/2022 A
256010000 ORDER DESIGN TRAFFIC 01/18/2022 A 02/03/2022 A
153010000 PAVEMENT SURVEY 02/01/2022 A 03/29/2022 A
232032000 DESIGN CONSULTANT ADVERTISE 02/07/2022 A 02/07/2022 A
450032000 TIP / STIP AMENDMENT 02/11/2022 A 02/11/2022 A
401032000 CONSULT SHORTLISTING 02/28/2022 A 02/28/2022 A
402032000 CONSULT FINAL SELECTION 04/18/2022 A 04/18/2022 A
250010000 P.E. BEGIN 07/01/2022 A 07/01/2022 A
237032000 FHWA AUTHORITY RECEIVED 07/08/2022 A 07/08/2022 A
299032000 REQUEST FOR AUTHORIZATION 07/12/2022 A 07/12/2022 A
234032000 NOTICE TO PROCEED 07/27/2022 A 07/27/2022 A
233032000 P.E. CONTRACT EXECUTED 07/28/2022 A 07/28/2022 A
106010000 DESIGN SURVEY 07/29/2022 A 10/20/2022 A
290010000 COMMUNITY AWARE PLAN COMPLETE 08/12/2022 A 08/12/2022 A
228010000 SUBMIT UTILITY DATA 08/19/2022 A 08/19/2022 A
197010000 PAVEMENT DESIGN 08/26/2022 A 09/20/2022 A
381000000 PREPARE PHI (30%) DESIGN PLN 10/21/2022 A 03/20/2023 A
132010000 ROADWAY SOILS REPORT 10/28/2022 A 10/28/2022 A
106020000 DESIGN SURVEY 11/28/2022 A 12/01/2022 A
260010000 TYPICAL SECTION APPROVED 11/28/2022 A 12/07/2022 A
294010000 PROCESS EXCEPTIONS/VARIANCE 02/06/2023 A 03/20/2023 A
132020000 ROADWAY SOILS REPORT 03/29/2023 A 03/29/2023 A
301010000 PHASE I PLANS REVIEW 04/04/2023 A 05/04/2023 A
264010000 UTILITY CONTACT 04/17/2023 A 04/17/2023 A
297030000 CONST. ESTIMATE UPDATE 05/02/2023 A 05/02/2023 A
247010000 LOCAL GOVERNMENT AGREEMENT 05/05/2023 A 12/13/2024 A
297010000 CONST. ESTIMATE UPDATE 05/23/2023 A 05/23/2023 A
297020000 CONST. ESTIMATE UPDATE 05/23/2023 A 05/23/2023 A
382000000 PREPARE PHII (60%) DESIGN PLN 12/11/2023 A 03/29/2024 A
302010000 PHASE II PLANS REVIEW 04/01/2024 A 04/19/2024 A
333032000 CULTURAL RESOURCES ASSESS SURV 04/02/2024 A 09/16/2024 A
355010000 NMSA (NON MAJOR STATE ACTION) 04/02/2024 A 09/24/2024 A
383000000 PREPARE PHIII (90%) DESIGN PLN 04/19/2024 A 07/17/2024 A
297060000 CONST. ESTIMATE UPDATE 04/24/2024 A 04/24/2024 A
137010000 IN-HOUSE R/W LICENSE AGREEMNT 05/15/2024 A 06/28/2024 A
292010000 PUBLIC INFO MEETING 05/22/2024 A 05/22/2024 A
272010000 FILE PERMITS 06/04/2024 A 06/04/2024 A
298010000 R/W ESTIMATE UPDATE 06/18/2024 A 06/18/2024 A
348010000 PARTNERSHIP MEETING 06/27/2024 A 06/27/2024 A
298060000 R/W ESTIMATE UPDATE 06/28/2024 A 07/18/2024 A
138010000 R/W PRELIMINARY MAP 07/11/2024 A 07/17/2024 A
142010000 SUBMIT PRE R/W REQUIREMENTS 07/17/2024 A 07/17/2024 A
210010000 REVIEW PRELIM R/W REQUIREMENTS 07/17/2024 A 07/22/2024 A
210020000 REVIEW PRELIM R/W REQUIREMENTS 07/17/2024 A 07/23/2024 A
210030000 REVIEW PRELIM R/W REQUIREMENTS 07/17/2024 A 07/26/2024 A
182010000 REQUEST BRIDGE NUMBER 07/18/2024 A 07/18/2024 A
182020000 REQUEST BRIDGE NUMBER 07/19/2024 A 07/19/2024 A
272020000 FILE PERMITS 07/23/2024 A 07/23/2024 A
303010000 PHASE III PLANS REVIEW 08/06/2024 A 08/27/2024 A
297090000 CONST. ESTIMATE UPDATE 08/22/2024 A 08/22/2024 A
384000000 PREPARE PHIV (100%) DESIGN PLN 08/23/2024 A 10/11/2024 A
323C20000 RETENTION/MITIGAT R/W REQRMTS 09/06/2024 A 11/22/2024 A
145010000 PERMITS 09/17/2024 A 09/19/2024 A
265010000 UTILITY PRE-DESIGN CONF 09/25/2024 A 09/25/2024 A
137020000 IN-HOUSE R/W LICENSE AGREEMNT 10/07/2024 A 10/07/2024 A
126010000 UTILITY RELOCATION 10/10/2024 A 12/02/2024 A
113070000 ROADWAY PLANS 10/11/2024 A 10/11/2024 A
310010000 PHASE IV PLANS REVIEW 10/28/2024 A 11/18/2024 A
130010000 SOIL CROSS SECTION 10/29/2024 A 11/18/2024 A
297100000 CONST. ESTIMATE UPDATE 11/07/2024 A 11/07/2024 A
193520000 LOCAL FUNDS DEPOSITED 12/02/2024 A 12/02/2024 A
193620000 LOCAL FUNDS DEPOSITED 12/02/2024 A 12/02/2024 A
748000000 ENV DOC REEVAL-CONST ADVERTSMT 06/30/2025 A 05/01/2026 
172010000 CHECK LIST ACTIVITIES 07/01/2025  07/01/2025 
220010000 UPDATE PLANS 07/02/2025  03/27/2026 
189010000 FINAL REVIEW 10/22/2025  04/17/2026 
266010000 UTILITIES CERTIFIED 10/22/2025  04/29/2026 
222010000 ALL PERMITS CLEAR 10/22/2025  05/04/2026 
163010000 MAINT OR FUNDS AGREEMENT 10/22/2025  05/04/2026 
187010000 NO R/W REQRD CERTIFICATION 11/12/2025  05/04/2026 
279010000 RAILROAD CLEAR 11/12/2025  05/04/2026 
220020000 UPDATE PLANS 11/12/2025  05/08/2026 
171010000 REQUEST CONTRACT TIME 11/19/2025  05/04/2026 
376010000 ENVIRONMENTAL CLEAR/CERTIF 12/17/2025  05/04/2026 
450052000 TIP / STIP AMENDMENT 02/10/2026  05/04/2026 
248010000 D.M.S APPROVAL 05/04/2026  05/04/2026 
204010000 PRODUCTION DATE 05/08/2026  05/08/2026 
226010000 PLANS TO DIST SPECS 05/11/2026  05/11/2026 
242010000 SPECIFICATIONS 05/11/2026  05/29/2026 
405010000 CEI CONSULTANT ADVERTISE 06/09/2026  06/09/2026 
242020000 SPECIFICATIONS 06/15/2026  06/26/2026 
406010000 CEI CONSULT SHORTLISTING 06/30/2026  06/30/2026 
205010000 CNST UTILITY CONTRACT EXECUTED 07/01/2026  09/09/2026 
297040000 CONST. ESTIMATE UPDATE 07/13/2026  07/17/2026 
242030000 SPECIFICATIONS 07/13/2026  07/17/2026 
370010000 PLANS TO DIST CONTRACT 07/17/2026  07/17/2026 
229070000 ADVERTISE DISTRICT CONTRACT 07/20/2026  09/10/2026 
407010000 CEI CONSULT FINAL SELECTION 07/21/2026  07/21/2026 
280TBD000 LETTING DATE 09/10/2026  09/10/2026 
408010000 CEI ENCUMBERED 09/29/2026  09/29/2026 
203010000 C.E.I. CONS. CONT. EXEC. 10/06/2026  10/06/2026