Activity
|
Description
|
Planned
Start
|
Planned
Finish
|
164032000
|
PREPARE SCOPE OF WORK
|
02/16/2021 A
|
04/05/2021 A
|
256010000
|
ORDER DESIGN TRAFFIC
|
03/08/2021 A
|
03/24/2021 A
|
450032000
|
TIP / STIP AMENDMENT
|
03/15/2021 A
|
03/15/2021 A
|
153010000
|
PAVEMENT SURVEY
|
04/06/2021 A
|
06/16/2021 A
|
232032000
|
DESIGN CONSULTANT ADVERTISE
|
04/12/2021 A
|
04/12/2021 A
|
401032000
|
CONSULT SHORTLISTING
|
05/10/2021 A
|
05/10/2021 A
|
402032000
|
CONSULT FINAL SELECTION
|
06/14/2021 A
|
06/14/2021 A
|
250010000
|
P.E. BEGIN
|
07/30/2021 A
|
07/30/2021 A
|
237032000
|
FHWA AUTHORITY RECEIVED
|
08/23/2021 A
|
08/23/2021 A
|
299032000
|
REQUEST FOR AUTHORIZATION
|
08/25/2021 A
|
08/25/2021 A
|
234032000
|
NOTICE TO PROCEED
|
08/27/2021 A
|
08/27/2021 A
|
233032000
|
P.E. CONTRACT EXECUTED
|
08/27/2021 A
|
08/27/2021 A
|
228010000
|
SUBMIT UTILITY DATA
|
09/08/2021 A
|
09/08/2021 A
|
106010000
|
DESIGN SURVEY
|
09/08/2021 A
|
01/12/2022 A
|
132010000
|
ROADWAY SOILS REPORT
|
09/20/2021 A
|
10/29/2021 A
|
197010000
|
PAVEMENT DESIGN
|
09/22/2021 A
|
10/04/2021 A
|
290010000
|
COMMUNITY AWARE PLAN COMPLETE
|
09/27/2021 A
|
09/27/2021 A
|
260010000
|
TYPICAL SECTION APPROVED
|
09/30/2021 A
|
03/16/2022 A
|
381000000
|
PREPARE PHI (30%) DESIGN PLN
|
01/12/2022 A
|
03/16/2022 A
|
106020000
|
DESIGN SURVEY
|
02/17/2022 A
|
03/03/2022 A
|
301010000
|
PHASE I PLANS REVIEW
|
03/18/2022 A
|
04/08/2022 A
|
264010000
|
UTILITY CONTACT
|
03/22/2022 A
|
03/22/2022 A
|
297030000
|
CONST. ESTIMATE UPDATE
|
03/30/2022 A
|
03/30/2022 A
|
297020000
|
CONST. ESTIMATE UPDATE
|
03/31/2022 A
|
04/04/2022 A
|
297010000
|
CONST. ESTIMATE UPDATE
|
04/04/2022 A
|
04/04/2022 A
|
247010000
|
LOCAL GOVERNMENT AGREEMENT
|
04/11/2022 A
|
04/11/2022 A
|
382000000
|
PREPARE PHII (60%) DESIGN PLN
|
04/11/2022 A
|
07/13/2022 A
|
302010000
|
PHASE II PLANS REVIEW
|
07/14/2022 A
|
08/03/2022 A
|
333032000
|
CULTURAL RESOURCES ASSESS SURV
|
07/14/2022 A
|
10/07/2022 A
|
749000000
|
TYPE 1 CE APPROVAL
|
07/14/2022 A
|
02/16/2023 A
|
297060000
|
CONST. ESTIMATE UPDATE
|
07/22/2022 A
|
07/22/2022 A
|
383000000
|
PREPARE PHIII (90%) DESIGN PLN
|
07/27/2022 A
|
10/26/2022 A
|
272010000
|
FILE PERMITS
|
08/04/2022 A
|
08/04/2022 A
|
348010000
|
PARTNERSHIP MEETING
|
08/04/2022 A
|
08/04/2022 A
|
265010000
|
UTILITY PRE-DESIGN CONF
|
08/09/2022 A
|
08/09/2022 A
|
132020000
|
ROADWAY SOILS REPORT
|
08/26/2022 A
|
08/26/2022 A
|
303010000
|
PHASE III PLANS REVIEW
|
10/25/2022 A
|
11/15/2022 A
|
126010000
|
UTILITY RELOCATION
|
10/25/2022 A
|
01/03/2023 A
|
182010000
|
REQUEST BRIDGE NUMBER
|
10/26/2022 A
|
10/26/2022 A
|
182020000
|
REQUEST BRIDGE NUMBER
|
10/26/2022 A
|
10/26/2022 A
|
297090000
|
CONST. ESTIMATE UPDATE
|
10/27/2022 A
|
10/27/2022 A
|
384000000
|
PREPARE PHIV (100%) DESIGN PLN
|
11/16/2022 A
|
12/27/2022 A
|
272020000
|
FILE PERMITS
|
11/28/2022 A
|
11/28/2022 A
|
137010000
|
IN-HOUSE R/W LICENSE AGREEMNT
|
12/05/2022 A
|
12/05/2022 A
|
310010000
|
PHASE IV PLANS REVIEW
|
12/19/2022 A
|
01/13/2023 A
|
297100000
|
CONST. ESTIMATE UPDATE
|
12/20/2022 A
|
12/20/2022 A
|
145010000
|
PERMITS
|
01/06/2023 A
|
01/12/2023 A
|
113070000
|
ROADWAY PLANS
|
01/16/2023 A
|
02/23/2023 A
|
266010000
|
UTILITIES CERTIFIED
|
01/24/2023 A
|
01/24/2023 A
|
171010000
|
REQUEST CONTRACT TIME
|
01/27/2023 A
|
01/31/2023 A
|
187010000
|
NO R/W REQRD CERTIFICATION
|
02/09/2023 A
|
02/09/2023 A
|
376010000
|
ENVIRONMENTAL CLEAR/CERTIF
|
02/21/2023 A
|
02/21/2023 A
|
130010000
|
SOIL CROSS SECTION
|
02/28/2023 A
|
03/31/2023 A
|
172010000
|
CHECK LIST ACTIVITIES
|
04/17/2023 A
|
04/17/2023 A
|
163010000
|
MAINT OR FUNDS AGREEMENT
|
04/28/2023 A
|
05/26/2023 A
|
193520000
|
LOCAL FUNDS DEPOSITED
|
07/03/2023 A
|
07/03/2023 A
|
248010000
|
D.M.S APPROVAL
|
07/17/2023 A
|
07/17/2023 A
|
222010000
|
ALL PERMITS CLEAR
|
07/19/2023 A
|
07/19/2023 A
|
204010000
|
PRODUCTION DATE
|
07/21/2023 A
|
07/21/2023 A
|
405010000
|
CEI CONSULTANT ADVERTISE
|
07/24/2023 A
|
07/24/2023 A
|
226010000
|
PLANS TO DIST SPECS
|
07/24/2023 A
|
07/24/2023 A
|
242010000
|
SPECIFICATIONS
|
07/25/2023 A
|
08/11/2023 A
|
205010000
|
CNST UTILITY CONTRACT EXECUTED
|
07/31/2023 A
|
07/31/2023 A
|
279010000
|
RAILROAD CLEAR
|
08/01/2023 A
|
08/01/2023 A
|
406010000
|
CEI CONSULT SHORTLISTING
|
08/14/2023 A
|
08/14/2023 A
|
407010000
|
CEI CONSULT FINAL SELECTION
|
08/28/2023 A
|
08/28/2023 A
|
242020000
|
SPECIFICATIONS
|
08/28/2023 A
|
09/08/2023 A
|
237052000
|
FHWA AUTHORITY RECEIVED
|
09/06/2023 A
|
10/30/2023
|
297040000
|
CONST. ESTIMATE UPDATE
|
09/25/2023 A
|
09/25/2023 A
|
242030000
|
SPECIFICATIONS
|
09/25/2023 A
|
09/25/2023 A
|
450052000
|
TIP / STIP AMENDMENT
|
09/27/2023 A
|
09/27/2023 A
|
212010000
|
TRANSMIT PKG FOR LETTING
|
10/02/2023 A
|
10/02/2023 A
|
408010000
|
CEI ENCUMBERED
|
10/09/2023
|
10/09/2023
|
203010000
|
C.E.I. CONS. CONT. EXEC.
|
10/16/2023
|
10/16/2023
|
280SET000
|
LETTING DATE
|
12/06/2023
|
12/06/2023
|