Activity
|
Description
|
Planned
Start
|
Planned
Finish
|
250010000
|
P.E. BEGIN
|
12/27/2012 A
|
12/27/2012 A
|
164010000
|
PREPARE SCOPE OF WORK
|
12/28/2012 A
|
01/24/2013 A
|
295010000
|
PREPARE ENVIRONMENT. DOC.
|
01/01/2013 A
|
01/01/2013 A
|
298010000
|
R/W ESTIMATE UPDATE
|
01/22/2013 A
|
02/04/2013 A
|
450032000
|
TIP / STIP AMENDMENT
|
01/23/2013 A
|
03/25/2013 A
|
164032000
|
PREPARE SCOPE OF WORK
|
01/24/2013 A
|
01/24/2013 A
|
232032000
|
DESIGN CONSULTANT ADVERTISE
|
01/28/2013 A
|
01/28/2013 A
|
256010000
|
ORDER DESIGN TRAFFIC
|
01/29/2013 A
|
03/11/2013 A
|
241010000
|
SAFETY RECOMMENDATIONS
|
01/31/2013 A
|
02/06/2013 A
|
230032000
|
CONSULTANT SCOPE MEETING
|
02/12/2013 A
|
02/12/2013 A
|
401032000
|
CONSULT SHORTLISTING
|
02/25/2013 A
|
02/25/2013 A
|
402032000
|
CONSULT FINAL SELECTION
|
03/18/2013 A
|
03/18/2013 A
|
452010000
|
P.E. OTHER AGENCY ENCUMBER
|
05/24/2013 A
|
05/24/2013 A
|
299032000
|
REQUEST FOR AUTHORIZATION
|
05/24/2013 A
|
05/24/2013 A
|
452032000
|
P.E. OTHER AGENCY ENCUMBER
|
06/25/2013 A
|
06/25/2013 A
|
233032000
|
P.E. CONTRACT EXECUTED
|
06/28/2013 A
|
06/28/2013 A
|
234032000
|
NOTICE TO PROCEED
|
07/01/2013 A
|
07/01/2013 A
|
106010000
|
DESIGN SURVEY
|
07/02/2013 A
|
11/18/2013 A
|
153010000
|
PAVEMENT SURVEY
|
07/26/2013 A
|
07/31/2013 A
|
197010000
|
PAVEMENT DESIGN
|
08/01/2013 A
|
08/02/2013 A
|
290010000
|
COMMUNITY AWARE PLAN COMPLETE
|
08/08/2013 A
|
08/08/2013 A
|
260010000
|
TYPICAL SECTION APPROVED
|
08/28/2013 A
|
08/28/2013 A
|
290020000
|
COMMUNITY AWARE PLAN COMPLETE
|
09/16/2013 A
|
09/16/2013 A
|
169010000
|
PRELIM. FIELD REVIEW
|
09/23/2013 A
|
09/23/2013 A
|
133010000
|
FOUNDATION INVESTIGATIONS
|
09/27/2013 A
|
10/24/2013 A
|
371010000
|
SUBMIT PAVE TYPE RPT INITIAL
|
10/17/2013 A
|
07/31/2014 A
|
116010000
|
SCOUR ANALYSIS
|
10/25/2013 A
|
11/21/2013 A
|
737000000
|
ENV DOC REEVALUATIONS - PE
|
10/31/2013 A
|
10/31/2013 A
|
286032000
|
FINAL ENV DOC TO FHWA
|
10/31/2013 A
|
10/31/2013 A
|
385000000
|
PREPARE PHI (30%) BRIDGE PLN
|
11/19/2013 A
|
02/10/2016 A
|
271010000
|
GEOTECH EVALUATION
|
11/22/2013 A
|
01/08/2014 A
|
106020000
|
DESIGN SURVEY
|
11/25/2013 A
|
01/28/2014 A
|
109010000
|
DRAINAGE DESIGN
|
12/18/2013 A
|
12/18/2013 A
|
109020000
|
DRAINAGE DESIGN
|
12/19/2013 A
|
01/20/2014 A
|
274010000
|
SUBMIT BHR
|
12/19/2013 A
|
02/19/2014 A
|
277010000
|
SUBMIT BDR
|
12/19/2013 A
|
03/26/2014 A
|
381000000
|
PREPARE PHI (30%) DESIGN PLN
|
01/09/2014 A
|
03/27/2014 A
|
324020000
|
MAINT MAPS PREP AND PROCESS
|
02/13/2014 A
|
03/05/2014 A
|
294010000
|
PROCESS EXCEPTIONS/VARIANCE
|
02/21/2014 A
|
02/21/2014 A
|
274020000
|
SUBMIT BHR
|
02/26/2014 A
|
03/19/2014 A
|
274030000
|
SUBMIT BHR
|
02/26/2014 A
|
09/07/2016 A
|
228010000
|
SUBMIT UTILITY DATA
|
02/28/2014 A
|
02/28/2014 A
|
277020000
|
SUBMIT BDR
|
03/26/2014 A
|
04/16/2014 A
|
247010000
|
LOCAL GOVERNMENT AGREEMENT
|
03/28/2014 A
|
03/28/2014 A
|
301010000
|
PHASE I PLANS REVIEW
|
03/28/2014 A
|
04/24/2014 A
|
324010000
|
MAINT MAPS PREP AND PROCESS
|
03/28/2014 A
|
06/19/2014 A
|
298030000
|
R/W ESTIMATE UPDATE
|
03/28/2014 A
|
07/31/2014 A
|
264010000
|
UTILITY CONTACT
|
04/04/2014 A
|
04/04/2014 A
|
131010000
|
ROADWAY SOILS SURVEY
|
04/25/2014 A
|
06/05/2014 A
|
382000000
|
PREPARE PHII (60%) DESIGN PLN
|
04/25/2014 A
|
02/10/2016 A
|
339010000
|
VALUE ENGINEERING REVIEW
|
10/13/2014 A
|
10/16/2014 A
|
45004X000
|
TIP / STIP AMENDMENT
|
10/21/2014 A
|
01/26/2015 A
|
333032000
|
CULTURAL RESOURCES ASSESS SURV
|
05/29/2015 A
|
05/29/2015 A
|
325010000
|
TIITF & OTHER GOV DOC
|
12/31/2015 A
|
12/31/2015 A
|
739000000
|
ENV DOC REEVALUATIONS - R/W
|
12/31/2015 A
|
04/12/2018 A
|
142010000
|
SUBMIT PRE R/W REQUIREMENTS
|
02/10/2016 A
|
02/10/2016 A
|
302010000
|
PHASE II PLANS REVIEW
|
02/10/2016 A
|
03/09/2016 A
|
389000000
|
REVIEW PHI (30%) BRIDGE PLN
|
02/10/2016 A
|
03/09/2016 A
|
210020000
|
REVIEW PRELIM R/W REQUIREMENTS
|
02/11/2016 A
|
02/24/2016 A
|
132010000
|
ROADWAY SOILS REPORT
|
02/11/2016 A
|
04/29/2016 A
|
298060000
|
R/W ESTIMATE UPDATE
|
02/11/2016 A
|
06/10/2016 A
|
182010000
|
REQUEST BRIDGE NUMBER
|
02/23/2016 A
|
02/23/2016 A
|
210010000
|
REVIEW PRELIM R/W REQUIREMENTS
|
02/24/2016 A
|
06/29/2016 A
|
183010000
|
BEGIN BRDGE LOAD RATING
|
02/24/2016 A
|
06/27/2017 A
|
297060000
|
CONST. ESTIMATE UPDATE
|
03/01/2016 A
|
03/01/2016 A
|
265010000
|
UTILITY PRE-DESIGN CONF
|
03/03/2016 A
|
03/03/2016 A
|
238010000
|
INTERIM EVALUATION OF CONSULT
|
03/10/2016 A
|
03/10/2016 A
|
133020000
|
FOUNDATION INVESTIGATIONS
|
03/10/2016 A
|
05/02/2016 A
|
387000000
|
PREPARE PHIII (90%) BRIDGE PLN
|
03/10/2016 A
|
06/16/2017 A
|
383000000
|
PREPARE PHIII (90%) DESIGN PLN
|
03/10/2016 A
|
06/16/2017 A
|
116020000
|
SCOUR ANALYSIS
|
05/02/2016 A
|
03/07/2017 A
|
151010000
|
PREPARE FINAL R/W REQUIREMENTS
|
06/13/2016 A
|
06/28/2016 A
|
292010000
|
PUBLIC INFO MEETING
|
06/28/2016 A
|
06/28/2016 A
|
319010000
|
SUBMIT FINAL R/W REQUIREMENTS
|
06/28/2016 A
|
06/28/2016 A
|
140010000
|
REVIEW CONSULTANT R/W MAP
|
06/29/2016 A
|
06/29/2016 A
|
210030000
|
REVIEW PRELIM R/W REQUIREMENTS
|
06/29/2016 A
|
06/29/2016 A
|
322010000
|
R/W REQUIRE. TO R/W ENG.
|
06/29/2016 A
|
09/13/2016 A
|
207010000
|
TITLE SEARCH CONTRACT
|
09/13/2016 A
|
10/03/2017 A
|
272010000
|
FILE PERMITS
|
03/08/2017 A
|
03/08/2017 A
|
271020000
|
GEOTECH EVALUATION
|
03/08/2017 A
|
06/16/2017 A
|
139010000
|
FINAL R/W MAP
|
04/06/2017 A
|
04/06/2017 A
|
260020000
|
TYPICAL SECTION APPROVED
|
05/16/2017 A
|
05/16/2017 A
|
148010000
|
M.O.T. PLANS
|
06/16/2017 A
|
07/07/2017 A
|
303010000
|
PHASE III PLANS REVIEW
|
06/16/2017 A
|
07/14/2017 A
|
391000000
|
REVIEW PHIII (90%) BRIDGE PLN
|
06/16/2017 A
|
07/14/2017 A
|
297090000
|
CONST. ESTIMATE UPDATE
|
06/23/2017 A
|
06/23/2017 A
|
184010000
|
SUBMIT BRDGE LOAD RATING
|
06/28/2017 A
|
06/28/2017 A
|
185010000
|
REVIEW BRDGE LOAD RATING
|
06/28/2017 A
|
01/30/2018 A
|
139020000
|
FINAL R/W MAP
|
07/14/2017 A
|
07/14/2017 A
|
388000000
|
PREPARE PHIV (100%) BRIDGE PLN
|
07/17/2017 A
|
02/11/2019 A
|
384000000
|
PREPARE PHIV (100%) DESIGN PLN
|
07/17/2017 A
|
02/11/2019 A
|
139030000
|
FINAL R/W MAP
|
08/31/2017 A
|
09/07/2017 A
|
144010000
|
INSTRUMENT PREP
|
09/01/2017 A
|
10/03/2017 A
|
157010000
|
R/W MAP COMPLETE
|
09/08/2017 A
|
09/28/2017 A
|
268010000
|
DOCUMENTS TO R/W
|
10/03/2017 A
|
10/03/2017 A
|
292020000
|
PUBLIC INFO MEETING
|
10/24/2017 A
|
10/24/2017 A
|
130010000
|
SOIL CROSS SECTION
|
11/27/2017 A
|
11/29/2017 A
|
186010000
|
APPROVE BRDGE LOAD RATING
|
01/31/2018 A
|
01/31/2018 A
|
271040000
|
GEOTECH EVALUATION
|
04/09/2018 A
|
04/09/2018 A
|
271050000
|
GEOTECH EVALUATION
|
04/09/2018 A
|
04/09/2018 A
|
271060000
|
GEOTECH EVALUATION
|
04/10/2018 A
|
04/10/2018 A
|
351010000
|
AUTHORIZE RW PURCHASE
|
04/27/2018 A
|
04/27/2018 A
|
352010000
|
AUTHORIZE RW RELOCATION
|
04/27/2018 A
|
04/27/2018 A
|
271030000
|
GEOTECH EVALUATION
|
05/16/2018 A
|
05/29/2018 A
|
127010000
|
PH 42 ROW CONSULT CONTR EXECUT
|
06/11/2018 A
|
06/11/2018 A
|
349010000
|
PH 4B ROW SERVCE CONTRACT EXEC
|
06/21/2018 A
|
06/21/2018 A
|
121010000
|
NEGOTIATION
|
07/03/2018 A
|
Fiscal Year: 2026
|
129010000
|
RELOCATION WORK
|
07/03/2018 A
|
Fiscal Year: 2026
|
852010000
|
DESIGN UTILITY CONT EXECUTE
|
11/08/2018 A
|
11/08/2018 A
|
205019000
|
CNST UTILITY CONTRACT EXECUTED
|
11/20/2018 A
|
11/20/2018 A
|
392000000
|
REVIEW PHIV (100%) BRIDGE PLN
|
02/11/2019 A
|
03/12/2019 A
|
310010000
|
PHASE IV PLANS REVIEW
|
02/12/2019 A
|
03/12/2019 A
|
297100000
|
CONST. ESTIMATE UPDATE
|
03/12/2019 A
|
03/12/2019 A
|
113070000
|
ROADWAY PLANS
|
03/13/2019 A
|
12/31/2019 A
|
247032000
|
LOCAL GOVERNMENT AGREEMENT
|
03/25/2019 A
|
06/28/2019 A
|
113071000
|
ROADWAY PLANS
|
09/17/2019 A
|
12/31/2019 A
|
205020000
|
CNST UTILITY CONTRACT EXECUTED
|
01/29/2021 A
|
08/26/2021 A
|
272020000
|
FILE PERMITS
|
10/23/2023
|
04/05/2024
|
145010000
|
PERMITS
|
11/21/2023
|
Fiscal Year: 2026
|
172010000
|
CHECK LIST ACTIVITIES
|
08/27/2024
|
09/24/2024
|
256020000
|
ORDER DESIGN TRAFFIC
|
08/28/2024
|
10/22/2024
|
33605X000
|
ENVIRONMENTAL REEVALUATION
|
08/28/2024
|
Fiscal Year: 2026
|
329010000
|
ENVIRONMENTAL REVIEW
|
08/28/2024
|
Fiscal Year: 2026
|
153020000
|
PAVEMENT SURVEY
|
09/25/2024
|
11/19/2024
|
197020000
|
PAVEMENT DESIGN
|
10/23/2024
|
12/17/2024
|
220010000
|
UPDATE PLANS
|
11/20/2024
|
Fiscal Year: 2026
|
748000000
|
ENV DOC REEVAL-CONST ADVERTSMT
|
03/26/2025
|
Fiscal Year: 2026
|
376010000
|
ENVIRONMENTAL CLEAR/CERTIF
|
05/15/2025
|
Fiscal Year: 2026
|
189010000
|
FINAL REVIEW
|
Fiscal Year: 2026
|
Fiscal Year: 2026
|
126010000
|
UTILITY RELOCATION
|
Fiscal Year: 2026
|
Fiscal Year: 2026
|
222010000
|
ALL PERMITS CLEAR
|
Fiscal Year: 2026
|
Fiscal Year: 2026
|
450052000
|
TIP / STIP AMENDMENT
|
Fiscal Year: 2026
|
Fiscal Year: 2026
|
220020000
|
UPDATE PLANS
|
Fiscal Year: 2026
|
Fiscal Year: 2026
|
163010000
|
MAINT OR FUNDS AGREEMENT
|
Fiscal Year: 2026
|
Fiscal Year: 2026
|
279010000
|
RAILROAD CLEAR
|
Fiscal Year: 2026
|
Fiscal Year: 2026
|
269010000
|
ALL UTILITIES CLEAR
|
Fiscal Year: 2026
|
Fiscal Year: 2026
|
266010000
|
UTILITIES CERTIFIED
|
Fiscal Year: 2026
|
Fiscal Year: 2026
|
171010000
|
REQUEST CONTRACT TIME
|
Fiscal Year: 2026
|
Fiscal Year: 2026
|
205026000
|
CNST UTILITY CONTRACT EXECUTED
|
Fiscal Year: 2026
|
Fiscal Year: 2026
|
193520000
|
LOCAL FUNDS DEPOSITED
|
Fiscal Year: 2026
|
Fiscal Year: 2026
|
193620000
|
LOCAL FUNDS DEPOSITED
|
Fiscal Year: 2026
|
Fiscal Year: 2026
|
304010000
|
CORING
|
Fiscal Year: 2026
|
Fiscal Year: 2026
|
248010000
|
D.M.S APPROVAL
|
Fiscal Year: 2026
|
Fiscal Year: 2026
|
204010000
|
PRODUCTION DATE
|
Fiscal Year: 2026
|
Fiscal Year: 2026
|
226010000
|
PLANS TO DIST SPECS
|
Fiscal Year: 2026
|
Fiscal Year: 2026
|
242010000
|
SPECIFICATIONS
|
Fiscal Year: 2026
|
Fiscal Year: 2026
|
242020000
|
SPECIFICATIONS
|
Fiscal Year: 2026
|
Fiscal Year: 2026
|
243010000
|
ALL R/W CLEARED
|
Fiscal Year: 2026
|
Fiscal Year: 2026
|
298100000
|
R/W ESTIMATE UPDATE
|
Fiscal Year: 2026
|
Fiscal Year: 2026
|
255010000
|
R/W CERTIFIED
|
Fiscal Year: 2026
|
Fiscal Year: 2026
|
405010000
|
CEI CONSULTANT ADVERTISE
|
Fiscal Year: 2026
|
Fiscal Year: 2026
|
297040000
|
CONST. ESTIMATE UPDATE
|
Fiscal Year: 2026
|
Fiscal Year: 2026
|
242030000
|
SPECIFICATIONS
|
Fiscal Year: 2026
|
Fiscal Year: 2026
|
212010000
|
TRANSMIT PKG FOR LETTING
|
Fiscal Year: 2026
|
Fiscal Year: 2026
|
406010000
|
CEI CONSULT SHORTLISTING
|
Fiscal Year: 2026
|
Fiscal Year: 2026
|
237052000
|
FHWA AUTHORITY RECEIVED
|
Fiscal Year: 2026
|
Fiscal Year: 2026
|
407010000
|
CEI CONSULT FINAL SELECTION
|
Fiscal Year: 2026
|
Fiscal Year: 2026
|
329020000
|
ENVIRONMENTAL REVIEW
|
Fiscal Year: 2026
|
Fiscal Year: 2026
|
408010000
|
CEI ENCUMBERED
|
Fiscal Year: 2026
|
Fiscal Year: 2026
|