Activity
|
Description
|
Planned
Start
|
Planned
Finish
|
164022000
|
PREPARE SCOPE OF WORK
|
10/30/2018 A
|
11/19/2018 A
|
450022000
|
TIP / STIP AMENDMENT
|
11/13/2018 A
|
06/20/2019 A
|
705000000
|
PD&E ADVERTISEMENT
|
11/26/2018 A
|
11/26/2018 A
|
401022000
|
CONSULT SHORTLISTING
|
01/07/2019 A
|
01/07/2019 A
|
402022000
|
CONSULT FINAL SELECTION
|
03/05/2019 A
|
03/05/2019 A
|
704000000
|
ASSIGN PD&E PROJECT MANAGER
|
03/06/2019 A
|
03/06/2019 A
|
224000000
|
ADVANCE NOTIFICATION
|
04/04/2019 A
|
04/04/2019 A
|
700000000
|
ETDM/ETAT PROG. SCREEN START
|
04/04/2019 A
|
04/04/2019 A
|
237022000
|
FHWA AUTHORITY RECEIVED
|
06/21/2019 A
|
06/21/2019 A
|
239022000
|
P.D.& E CONTRACT EXECUTED
|
06/21/2019 A
|
06/21/2019 A
|
299022000
|
REQUEST FOR AUTHORIZATION
|
06/21/2019 A
|
06/21/2019 A
|
135010000
|
E.M.O. STUDY
|
06/21/2019 A
|
09/06/2021 A
|
168022000
|
Q. A. REVIEW
|
06/24/2019 A
|
07/05/2019 A
|
168010000
|
Q. A. REVIEW
|
06/24/2019 A
|
07/12/2019 A
|
359010000
|
COMMUNITY INVOLVEMENT
|
06/24/2019 A
|
07/19/2019 A
|
168020000
|
Q. A. REVIEW
|
07/12/2019 A
|
07/12/2019 A
|
155223000
|
UPDATE SCOPE OF WORK
|
07/26/2019 A
|
08/30/2019 A
|
359060000
|
COMMUNITY INVOLVEMENT
|
08/22/2019 A
|
08/22/2019 A
|
701000000
|
ETDM PROG PRELIM SUM REP PUB
|
08/23/2019 A
|
08/23/2019 A
|
297220300
|
CONST. ESTIMATE UPDATE
|
09/04/2019 A
|
09/04/2019 A
|
298220300
|
R/W ESTIMATE UPDATE
|
09/06/2019 A
|
11/04/2019 A
|
159222000
|
COLOR CODE UTILITY PLANS
|
10/09/2019 A
|
10/15/2019 A
|
271221000
|
GEOTECH EVALUATION
|
10/28/2019 A
|
11/21/2019 A
|
109222000
|
DRAINAGE DESIGN
|
10/28/2019 A
|
12/16/2019 A
|
109223000
|
DRAINAGE DESIGN
|
10/28/2019 A
|
12/16/2019 A
|
100222000
|
LOCATION HYDRAULICS REPORT-LHR
|
10/28/2019 A
|
12/16/2019 A
|
119221000
|
CONCEPT REVIEW
|
10/28/2019 A
|
12/31/2019 A
|
702000000
|
ETDM PROG FINAL SUM REP PUB
|
10/30/2019 A
|
10/30/2019 A
|
292000000
|
PUBLIC INFO MEETING
|
11/04/2019 A
|
11/08/2019 A
|
159020000
|
COLOR CODE UTILITY PLANS
|
11/20/2019 A
|
11/20/2019 A
|
333010000
|
CULTURAL RESOURCES ASSESS SURV
|
12/02/2019 A
|
12/16/2019 A
|
109221000
|
DRAINAGE DESIGN
|
12/03/2019 A
|
12/03/2019 A
|
333222000
|
CULTURAL RESOURCES ASSESS SURV
|
12/17/2019 A
|
01/17/2020 A
|
761221000
|
NATURAL RESOURCE EVALUATION
|
01/01/2020 A
|
01/17/2020 A
|
155226000
|
UPDATE SCOPE OF WORK
|
01/01/2020 A
|
01/28/2020 A
|
174221000
|
CONTAMINATION TESTING
|
01/01/2020 A
|
02/10/2020 A
|
335221000
|
PD&E NOISE STUDY COMPLETE
|
01/01/2020 A
|
03/23/2020 A
|
271000000
|
GEOTECH EVALUATION
|
01/28/2020 A
|
01/28/2020 A
|
761010000
|
NATURAL RESOURCE EVALUATION
|
01/31/2020 A
|
03/17/2020 A
|
333224000
|
CULTURAL RESOURCES ASSESS SURV
|
02/18/2020 A
|
04/21/2020 A
|
174223000
|
CONTAMINATION TESTING
|
02/27/2020 A
|
03/19/2020 A
|
174000000
|
CONTAMINATION TESTING
|
03/19/2020 A
|
03/20/2020 A
|
298220600
|
R/W ESTIMATE UPDATE
|
03/27/2020 A
|
04/30/2020 A
|
109000000
|
DRAINAGE DESIGN
|
04/02/2020 A
|
04/02/2020 A
|
100000000
|
LOCATION HYDRAULICS REPORT-LHR
|
04/02/2020 A
|
04/02/2020 A
|
274000000
|
SUBMIT BHR
|
04/02/2020 A
|
04/02/2020 A
|
757000000
|
TRAFFIC ANALYSIS/REPORT
|
04/10/2020 A
|
04/10/2020 A
|
761224000
|
NATURAL RESOURCE EVALUATION
|
04/14/2020 A
|
06/23/2020 A
|
333080000
|
CULTURAL RESOURCES ASSESS SURV
|
04/21/2020 A
|
04/21/2020 A
|
756000000
|
SECTION 106 EFFECTS/ 267 F.S.
|
04/22/2020 A
|
04/22/2020 A
|
756010000
|
SECTION 106 EFFECTS/ 267 F.S.
|
04/22/2020 A
|
04/22/2020 A
|
762000000
|
SHPO CONSULTATION COMPLETE
|
04/22/2020 A
|
04/22/2020 A
|
711000000
|
ALTERNATIVES WORKSHOP
|
05/26/2020 A
|
05/26/2020 A
|
706000000
|
TYPE 2 CE START
|
05/26/2020 A
|
05/27/2020 A
|
335224000
|
PD&E NOISE STUDY COMPLETE
|
05/27/2020 A
|
07/09/2020 A
|
765221000
|
INTERCHANGE ACCESS REPORT
|
05/28/2020 A
|
06/05/2020 A
|
159000000
|
COLOR CODE UTILITY PLANS
|
05/29/2020 A
|
05/29/2020 A
|
751000000
|
SECTION 4(F)
|
06/08/2020 A
|
06/08/2020 A
|
335000000
|
PD&E NOISE STUDY COMPLETE
|
07/09/2020 A
|
07/09/2020 A
|
119223000
|
CONCEPT REVIEW
|
07/27/2020 A
|
08/21/2020 A
|
155220900
|
UPDATE SCOPE OF WORK
|
07/27/2020 A
|
09/01/2020 A
|
119000000
|
CONCEPT REVIEW
|
09/01/2020 A
|
09/01/2020 A
|
298220900
|
R/W ESTIMATE UPDATE
|
09/02/2020 A
|
09/25/2020 A
|
357010000
|
TYPE 2 CE (CATEG EXCLUSION)
|
09/02/2020 A
|
02/10/2021 A
|
761080000
|
NATURAL RESOURCE EVALUATION
|
11/16/2020 A
|
11/16/2020 A
|
159220900
|
COLOR CODE UTILITY PLANS
|
11/27/2020 A
|
11/30/2020 A
|
765000000
|
INTERCHANGE ACCESS REPORT
|
12/09/2020 A
|
12/09/2020 A
|
761000000
|
NATURAL RESOURCE EVALUATION
|
02/10/2021 A
|
02/10/2021 A
|
752000000
|
INFORMAL USFWS CONSLT COMP
|
02/12/2021 A
|
02/12/2021 A
|
366010000
|
PREPARE FOR PUBLIC HEARING
|
02/18/2021 A
|
03/26/2021 A
|
293000000
|
ADVERT. PUBLIC HEARING
|
04/22/2021 A
|
04/22/2021 A
|
262000000
|
CONDUCT PUBLIC HEARING
|
05/20/2021 A
|
05/20/2021 A
|
759000000
|
TYPICAL SECTION SELECTION
|
05/21/2021 A
|
05/21/2021 A
|
357404000
|
TYPE 2 CE (CATEG EXCLUSION)
|
05/21/2021 A
|
07/07/2021 A
|
155221000
|
UPDATE SCOPE OF WORK
|
06/22/2021 A
|
07/06/2021 A
|
710000000
|
PLANNING CONSISTENCY COMPL
|
07/06/2021 A
|
07/06/2021 A
|
298221000
|
R/W ESTIMATE UPDATE
|
07/07/2021 A
|
08/16/2021 A
|
297220900
|
CONST. ESTIMATE UPDATE
|
08/03/2021 A
|
08/03/2021 A
|
297221000
|
CONST. ESTIMATE UPDATE
|
08/03/2021 A
|
08/03/2021 A
|
263000000
|
LOC/DES APPROVAL
|
09/06/2021 A
|
09/06/2021 A
|
722000000
|
TYPE 2 TO FHWA
|
09/06/2021 A
|
09/06/2021 A
|
736000000
|
LDCA PUBLIC NOTICE
|
09/14/2021 A
|
09/16/2021 A
|
760000000
|
PRELIMINARY ENGINEERING REPORT
|
09/16/2021 A
|
09/16/2021 A
|