Activity
|
Description
|
Planned
Start
|
Planned
Finish
|
241010000
|
SAFETY RECOMMENDATIONS
|
04/04/2019 A
|
04/04/2019 A
|
164032000
|
PREPARE SCOPE OF WORK
|
06/04/2019 A
|
07/22/2019 A
|
450032000
|
TIP / STIP AMENDMENT
|
06/28/2019 A
|
07/31/2019 A
|
250010000
|
P.E. BEGIN
|
07/01/2019 A
|
07/01/2019 A
|
256010000
|
ORDER DESIGN TRAFFIC
|
07/15/2019 A
|
07/23/2019 A
|
153010000
|
PAVEMENT SURVEY
|
07/23/2019 A
|
07/23/2019 A
|
298010000
|
R/W ESTIMATE UPDATE
|
07/23/2019 A
|
07/23/2019 A
|
232032000
|
DESIGN CONSULTANT ADVERTISE
|
07/29/2019 A
|
07/29/2019 A
|
237032000
|
FHWA AUTHORITY RECEIVED
|
08/05/2019 A
|
08/05/2019 A
|
401032000
|
CONSULT SHORTLISTING
|
08/28/2019 A
|
08/28/2019 A
|
402032000
|
CONSULT FINAL SELECTION
|
10/14/2019 A
|
10/14/2019 A
|
106010000
|
DESIGN SURVEY
|
11/27/2019 A
|
04/10/2020 A
|
197010000
|
PAVEMENT DESIGN
|
12/23/2019 A
|
01/08/2020 A
|
325010000
|
TIITF & OTHER GOV DOC
|
01/16/2020 A
|
01/16/2020 A
|
299032000
|
REQUEST FOR AUTHORIZATION
|
01/21/2020 A
|
01/21/2020 A
|
233032000
|
P.E. CONTRACT EXECUTED
|
01/27/2020 A
|
01/27/2020 A
|
290010000
|
COMMUNITY AWARE PLAN COMPLETE
|
01/28/2020 A
|
02/13/2020 A
|
234032000
|
NOTICE TO PROCEED
|
01/29/2020 A
|
01/29/2020 A
|
228010000
|
SUBMIT UTILITY DATA
|
02/06/2020 A
|
02/06/2020 A
|
106020000
|
DESIGN SURVEY
|
04/16/2020 A
|
05/19/2020 A
|
271010000
|
GEOTECH EVALUATION
|
05/28/2020 A
|
08/05/2020 A
|
131010000
|
ROADWAY SOILS SURVEY
|
05/28/2020 A
|
08/05/2020 A
|
260010000
|
TYPICAL SECTION APPROVED
|
06/11/2020 A
|
08/07/2020 A
|
381000000
|
PREPARE PHI (30%) DESIGN PLN
|
08/10/2020 A
|
11/04/2020 A
|
274010000
|
SUBMIT BHR
|
09/30/2020 A
|
10/30/2020 A
|
277010000
|
SUBMIT BDR
|
09/30/2020 A
|
11/04/2020 A
|
270032000
|
SUBMIT BRIDGE PACKAGE
|
11/02/2020 A
|
11/10/2020 A
|
297020000
|
CONST. ESTIMATE UPDATE
|
11/03/2020 A
|
11/03/2020 A
|
301010000
|
PHASE I PLANS REVIEW
|
11/05/2020 A
|
11/30/2020 A
|
298030000
|
R/W ESTIMATE UPDATE
|
11/05/2020 A
|
12/02/2020 A
|
138010000
|
R/W PRELIMINARY MAP
|
11/05/2020 A
|
02/22/2021 A
|
297010000
|
CONST. ESTIMATE UPDATE
|
11/24/2020 A
|
11/24/2020 A
|
274020000
|
SUBMIT BHR
|
11/25/2020 A
|
07/13/2021 A
|
297030000
|
CONST. ESTIMATE UPDATE
|
11/30/2020 A
|
11/30/2020 A
|
382000000
|
PREPARE PHII (60%) DESIGN PLN
|
12/01/2020 A
|
01/11/2021 A
|
182010000
|
REQUEST BRIDGE NUMBER
|
01/05/2021 A
|
01/05/2021 A
|
298060000
|
R/W ESTIMATE UPDATE
|
01/11/2021 A
|
02/05/2021 A
|
302010000
|
PHASE II PLANS REVIEW
|
01/12/2021 A
|
02/09/2021 A
|
333032000
|
CULTURAL RESOURCES ASSESS SURV
|
01/12/2021 A
|
07/19/2021 A
|
247010000
|
LOCAL GOVERNMENT AGREEMENT
|
01/20/2021 A
|
06/09/2021 A
|
277020000
|
SUBMIT BDR
|
01/25/2021 A
|
01/25/2021 A
|
264010000
|
UTILITY CONTACT
|
01/26/2021 A
|
01/29/2021 A
|
297060000
|
CONST. ESTIMATE UPDATE
|
01/28/2021 A
|
01/28/2021 A
|
271020000
|
GEOTECH EVALUATION
|
02/08/2021 A
|
03/26/2021 A
|
132010000
|
ROADWAY SOILS REPORT
|
02/08/2021 A
|
03/26/2021 A
|
348010000
|
PARTNERSHIP MEETING
|
02/10/2021 A
|
02/10/2021 A
|
265010000
|
UTILITY PRE-DESIGN CONF
|
02/10/2021 A
|
02/10/2021 A
|
383000000
|
PREPARE PHIII (90%) DESIGN PLN
|
02/10/2021 A
|
03/26/2021 A
|
142010000
|
SUBMIT PRE R/W REQUIREMENTS
|
02/22/2021 A
|
02/22/2021 A
|
210010000
|
REVIEW PRELIM R/W REQUIREMENTS
|
02/23/2021 A
|
03/25/2021 A
|
272010000
|
FILE PERMITS
|
02/24/2021 A
|
02/24/2021 A
|
210020000
|
REVIEW PRELIM R/W REQUIREMENTS
|
03/01/2021 A
|
03/12/2021 A
|
210030000
|
REVIEW PRELIM R/W REQUIREMENTS
|
03/01/2021 A
|
03/12/2021 A
|
749000000
|
TYPE 1 CE APPROVAL
|
03/02/2021 A
|
06/22/2022 A
|
45004X000
|
TIP / STIP AMENDMENT
|
03/19/2021 A
|
03/19/2021 A
|
151010000
|
PREPARE FINAL R/W REQUIREMENTS
|
03/25/2021 A
|
03/25/2021 A
|
140010000
|
REVIEW CONSULTANT R/W MAP
|
03/25/2021 A
|
03/25/2021 A
|
319010000
|
SUBMIT FINAL R/W REQUIREMENTS
|
03/25/2021 A
|
03/25/2021 A
|
184010000
|
SUBMIT BRDGE LOAD RATING
|
03/26/2021 A
|
03/26/2021 A
|
322010000
|
R/W REQUIRE. TO R/W ENG.
|
03/26/2021 A
|
04/22/2021 A
|
139010000
|
FINAL R/W MAP
|
03/26/2021 A
|
06/03/2021 A
|
207010000
|
TITLE SEARCH CONTRACT
|
03/26/2021 A
|
07/15/2021 A
|
126010000
|
UTILITY RELOCATION
|
03/26/2021 A
|
08/26/2021 A
|
303010000
|
PHASE III PLANS REVIEW
|
03/29/2021 A
|
04/19/2021 A
|
297090000
|
CONST. ESTIMATE UPDATE
|
04/20/2021 A
|
04/20/2021 A
|
384000000
|
PREPARE PHIV (100%) DESIGN PLN
|
04/20/2021 A
|
06/30/2021 A
|
186010000
|
APPROVE BRDGE LOAD RATING
|
05/18/2021 A
|
09/09/2021 A
|
272020000
|
FILE PERMITS
|
05/25/2021 A
|
05/25/2021 A
|
157010000
|
R/W MAP COMPLETE
|
06/04/2021 A
|
07/07/2021 A
|
144010000
|
INSTRUMENT PREP
|
06/15/2021 A
|
07/07/2021 A
|
130010000
|
SOIL CROSS SECTION
|
07/01/2021 A
|
07/21/2021 A
|
310010000
|
PHASE IV PLANS REVIEW
|
07/01/2021 A
|
07/23/2021 A
|
268010000
|
DOCUMENTS TO R/W
|
07/07/2021 A
|
07/07/2021 A
|
297100000
|
CONST. ESTIMATE UPDATE
|
07/22/2021 A
|
07/22/2021 A
|
113070000
|
ROADWAY PLANS
|
07/26/2021 A
|
08/26/2021 A
|
351010000
|
AUTHORIZE RW PURCHASE
|
09/13/2021 A
|
09/13/2021 A
|
145010000
|
PERMITS
|
10/04/2021 A
|
12/29/2023
|
121010000
|
NEGOTIATION
|
11/05/2021 A
|
06/14/2022 A
|
751000000
|
SECTION 4(F)
|
04/14/2022 A
|
05/24/2022 A
|
243010000
|
ALL R/W CLEARED
|
06/14/2022 A
|
06/14/2022 A
|
748000000
|
ENV DOC REEVAL-CONST ADVERTSMT
|
12/06/2022 A
|
05/16/2023 A
|
172010000
|
CHECK LIST ACTIVITIES
|
12/30/2022 A
|
12/30/2022 A
|
220010000
|
UPDATE PLANS
|
03/21/2023 A
|
05/18/2023 A
|
405010000
|
CEI CONSULTANT ADVERTISE
|
05/15/2023 A
|
05/15/2023 A
|
376010000
|
ENVIRONMENTAL CLEAR/CERTIF
|
05/16/2023 A
|
05/16/2023 A
|
266010000
|
UTILITIES CERTIFIED
|
05/17/2023 A
|
05/17/2023 A
|
189010000
|
FINAL REVIEW
|
05/19/2023 A
|
06/09/2023 A
|
171010000
|
REQUEST CONTRACT TIME
|
05/26/2023 A
|
05/30/2023 A
|
163010000
|
MAINT OR FUNDS AGREEMENT
|
05/26/2023 A
|
06/30/2023 A
|
406010000
|
CEI CONSULT SHORTLISTING
|
06/12/2023 A
|
06/12/2023 A
|
220020000
|
UPDATE PLANS
|
06/12/2023 A
|
01/05/2024
|
407010000
|
CEI CONSULT FINAL SELECTION
|
07/10/2023 A
|
07/10/2023 A
|
255010000
|
R/W CERTIFIED
|
09/29/2023 A
|
09/29/2023 A
|
279010000
|
RAILROAD CLEAR
|
09/29/2023
|
01/01/2024
|
450052000
|
TIP / STIP AMENDMENT
|
10/02/2023
|
03/14/2024
|
304010000
|
CORING
|
12/25/2023
|
12/25/2023
|
222010000
|
ALL PERMITS CLEAR
|
12/29/2023
|
01/01/2024
|
248010000
|
D.M.S APPROVAL
|
01/01/2024
|
01/01/2024
|
204010000
|
PRODUCTION DATE
|
01/05/2024
|
01/05/2024
|
226010000
|
PLANS TO DIST SPECS
|
01/08/2024
|
01/08/2024
|
242010000
|
SPECIFICATIONS
|
01/08/2024
|
01/26/2024
|
298100000
|
R/W ESTIMATE UPDATE
|
01/08/2024
|
05/21/2024
|
242020000
|
SPECIFICATIONS
|
02/12/2024
|
02/23/2024
|
297040000
|
CONST. ESTIMATE UPDATE
|
03/11/2024
|
03/15/2024
|
242030000
|
SPECIFICATIONS
|
03/11/2024
|
03/15/2024
|
212010000
|
TRANSMIT PKG FOR LETTING
|
03/15/2024
|
03/15/2024
|
237052000
|
FHWA AUTHORITY RECEIVED
|
03/21/2024
|
04/15/2024
|
408010000
|
CEI ENCUMBERED
|
05/06/2024
|
05/06/2024
|
203010000
|
C.E.I. CONS. CONT. EXEC.
|
05/13/2024
|
05/13/2024
|
280SET000
|
LETTING DATE
|
05/22/2024
|
05/22/2024
|