Activity
|
Description
|
Planned
Start
|
Planned
Finish
|
450032000
|
TIP / STIP AMENDMENT
|
06/04/2021 A
|
06/04/2021 A
|
256010000
|
ORDER DESIGN TRAFFIC
|
06/10/2021 A
|
06/22/2021 A
|
164032000
|
PREPARE SCOPE OF WORK
|
06/22/2021 A
|
08/09/2021 A
|
250010000
|
P.E. BEGIN
|
07/30/2021 A
|
07/30/2021 A
|
232032000
|
DESIGN CONSULTANT ADVERTISE
|
08/16/2021 A
|
08/16/2021 A
|
401032000
|
CONSULT SHORTLISTING
|
09/13/2021 A
|
09/13/2021 A
|
402032000
|
CONSULT FINAL SELECTION
|
10/11/2021 A
|
10/11/2021 A
|
237032000
|
FHWA AUTHORITY RECEIVED
|
11/16/2021 A
|
11/16/2021 A
|
299032000
|
REQUEST FOR AUTHORIZATION
|
11/18/2021 A
|
11/18/2021 A
|
234032000
|
NOTICE TO PROCEED
|
11/22/2021 A
|
11/22/2021 A
|
233032000
|
P.E. CONTRACT EXECUTED
|
11/22/2021 A
|
11/22/2021 A
|
106010000
|
DESIGN SURVEY
|
11/23/2021 A
|
04/18/2022 A
|
228010000
|
SUBMIT UTILITY DATA
|
11/30/2021 A
|
11/30/2021 A
|
290010000
|
COMMUNITY AWARE PLAN COMPLETE
|
12/07/2021 A
|
12/07/2021 A
|
132010000
|
ROADWAY SOILS REPORT
|
12/31/2021 A
|
02/25/2022 A
|
153010000
|
PAVEMENT SURVEY
|
01/03/2022 A
|
01/31/2022 A
|
260010000
|
TYPICAL SECTION APPROVED
|
03/31/2022 A
|
04/27/2022 A
|
381000000
|
PREPARE PHI (30%) DESIGN PLN
|
03/31/2022 A
|
06/07/2022 A
|
106020000
|
DESIGN SURVEY
|
04/06/2022 A
|
04/11/2022 A
|
297020000
|
CONST. ESTIMATE UPDATE
|
06/08/2022 A
|
06/08/2022 A
|
301010000
|
PHASE I PLANS REVIEW
|
06/08/2022 A
|
06/27/2022 A
|
264010000
|
UTILITY CONTACT
|
06/09/2022 A
|
06/09/2022 A
|
297010000
|
CONST. ESTIMATE UPDATE
|
06/14/2022 A
|
06/14/2022 A
|
297030000
|
CONST. ESTIMATE UPDATE
|
06/23/2022 A
|
06/23/2022 A
|
382000000
|
PREPARE PHII (60%) DESIGN PLN
|
06/28/2022 A
|
09/21/2022 A
|
132020000
|
ROADWAY SOILS REPORT
|
07/29/2022 A
|
10/20/2022 A
|
197010000
|
PAVEMENT DESIGN
|
08/26/2022 A
|
09/08/2022 A
|
302010000
|
PHASE II PLANS REVIEW
|
09/22/2022 A
|
10/14/2022 A
|
749000000
|
TYPE 1 CE APPROVAL
|
09/22/2022 A
|
05/16/2023 A
|
333032000
|
CULTURAL RESOURCES ASSESS SURV
|
09/26/2022 A
|
01/23/2023 A
|
297060000
|
CONST. ESTIMATE UPDATE
|
10/11/2022 A
|
10/11/2022 A
|
383000000
|
PREPARE PHIII (90%) DESIGN PLN
|
10/14/2022 A
|
03/23/2023 A
|
348010000
|
PARTNERSHIP MEETING
|
10/31/2022 A
|
10/31/2022 A
|
265010000
|
UTILITY PRE-DESIGN CONF
|
11/01/2022 A
|
11/01/2022 A
|
247010000
|
LOCAL GOVERNMENT AGREEMENT
|
11/28/2022 A
|
03/20/2023 A
|
272010000
|
FILE PERMITS
|
12/14/2022 A
|
12/14/2022 A
|
182010000
|
REQUEST BRIDGE NUMBER
|
12/28/2022 A
|
12/28/2022 A
|
182020000
|
REQUEST BRIDGE NUMBER
|
12/28/2022 A
|
12/28/2022 A
|
137010000
|
IN-HOUSE R/W LICENSE AGREEMNT
|
01/27/2023 A
|
01/27/2023 A
|
303010000
|
PHASE III PLANS REVIEW
|
03/24/2023 A
|
04/14/2023 A
|
297090000
|
CONST. ESTIMATE UPDATE
|
04/07/2023 A
|
04/07/2023 A
|
384000000
|
PREPARE PHIV (100%) DESIGN PLN
|
04/14/2023 A
|
05/01/2023 A
|
171010000
|
REQUEST CONTRACT TIME
|
04/17/2023 A
|
04/17/2023 A
|
272020000
|
FILE PERMITS
|
04/28/2023 A
|
04/28/2023 A
|
126010000
|
UTILITY RELOCATION
|
04/28/2023 A
|
06/27/2023 A
|
163010000
|
MAINT OR FUNDS AGREEMENT
|
05/01/2023 A
|
05/26/2023 A
|
310010000
|
PHASE IV PLANS REVIEW
|
05/02/2023 A
|
05/26/2023 A
|
376010000
|
ENVIRONMENTAL CLEAR/CERTIF
|
05/16/2023 A
|
05/16/2023 A
|
187010000
|
NO R/W REQRD CERTIFICATION
|
05/16/2023 A
|
05/16/2023 A
|
450052000
|
TIP / STIP AMENDMENT
|
05/17/2023 A
|
05/17/2023 A
|
297100000
|
CONST. ESTIMATE UPDATE
|
05/18/2023 A
|
05/18/2023 A
|
130010000
|
SOIL CROSS SECTION
|
05/26/2023 A
|
05/30/2023 A
|
113070000
|
ROADWAY PLANS
|
05/26/2023 A
|
06/28/2023 A
|
172010000
|
CHECK LIST ACTIVITIES
|
05/29/2023 A
|
05/29/2023 A
|
145010000
|
PERMITS
|
06/01/2023 A
|
06/01/2023 A
|
248010000
|
D.M.S APPROVAL
|
06/26/2023 A
|
06/26/2023 A
|
266010000
|
UTILITIES CERTIFIED
|
06/27/2023 A
|
06/27/2023 A
|
279010000
|
RAILROAD CLEAR
|
06/28/2023 A
|
06/28/2023 A
|
222010000
|
ALL PERMITS CLEAR
|
06/29/2023 A
|
06/29/2023 A
|
204010000
|
PRODUCTION DATE
|
06/30/2023 A
|
06/30/2023 A
|
226010000
|
PLANS TO DIST SPECS
|
07/05/2023 A
|
07/05/2023 A
|
242010000
|
SPECIFICATIONS
|
07/06/2023 A
|
07/21/2023 A
|
242020000
|
SPECIFICATIONS
|
08/07/2023 A
|
08/18/2023 A
|
297040000
|
CONST. ESTIMATE UPDATE
|
08/25/2023 A
|
08/25/2023 A
|
242030000
|
SPECIFICATIONS
|
08/25/2023 A
|
08/25/2023 A
|
237052000
|
FHWA AUTHORITY RECEIVED
|
09/06/2023 A
|
09/06/2023 A
|
405010000
|
CEI CONSULTANT ADVERTISE
|
09/11/2023 A
|
09/11/2023 A
|
212010000
|
TRANSMIT PKG FOR LETTING
|
09/11/2023 A
|
09/11/2023 A
|
406010000
|
CEI CONSULT SHORTLISTING
|
10/16/2023
|
10/16/2023
|
407010000
|
CEI CONSULT FINAL SELECTION
|
10/30/2023
|
10/30/2023
|
280SET000
|
LETTING DATE
|
11/15/2023
|
11/15/2023
|
408010000
|
CEI ENCUMBERED
|
11/27/2023
|
11/27/2023
|
203010000
|
C.E.I. CONS. CONT. EXEC.
|
12/04/2023
|
12/04/2023
|