Selection Criteria
 All in State 
 2025-2030 G1 
 Item Number:448152-1 




Scheduled Activities may or may not be confirmed dates and are subject to change without notice.
Please contact the Program Services Office at the appropriate District office for validation.
 
448152-1 SABAL PALMS ELEMENTARY SAFE ROUTES / SIDEWALKS
District 03 - Leon County
 
Project Manager: MARIA SHOWALTER
Type of Work: SIDEWALK
Activity Description Planned
Start
Planned
Finish
285058000 RFP/DES BUILD PKG APPROVAL 01/27/2025 A 02/11/2025 A
383038000 PREPARE PHIII (90%) DESIGN PLN 02/18/2025 A 03/14/2025 A
303038000 PHASE III PLANS REVIEW 03/17/2025 A 03/31/2025 A
384038000 PREPARE PHIV (100%) DESIGN PLN 04/01/2025 A 06/17/2025 A
748000000 ENV DOC REEVAL-CONST ADVERTSMT 04/01/2025 A 08/05/2025 
450058000 TIP / STIP AMENDMENT 04/11/2025 A 04/11/2025 A
333058000 CULTURAL RESOURCES ASSESS SURV 05/01/2025 A 08/05/2025 
310038000 PHASE IV PLANS REVIEW 06/17/2025 A 07/01/2025 
874010000 LOCAL SIGNATURE 06/27/2025  07/02/2025 
874030000 LOCAL SIGNATURE 06/30/2025  07/09/2025 
113038000 ROADWAY PLANS 07/02/2025  07/09/2025 
874058000 LOCAL SIGNATURE 07/07/2025  07/30/2025 
201010000 PLANS COMPLETED 07/10/2025  05/01/2026 
376010000 ENVIRONMENTAL CLEAR/CERTIF 07/21/2025  08/06/2025 
187010000 NO R/W REQRD CERTIFICATION 07/31/2025  08/20/2025 
449058000 LAP PH 28 PD&E AUTHORIZATION 08/18/2025  08/21/2025 
454010000 CONSTRUCT OTHR AGENCY ENCUMBER 08/29/2025  08/29/2025 
247058000 LOCAL GOVERNMENT AGREEMENT 09/08/2025  09/08/2025 
200010000 PROJECT ADVERTISEMENT 09/09/2025  10/06/2025 
289010000 LAP LETTING 10/07/2025  10/07/2025 
189058000 FINAL REVIEW 11/12/2025  11/12/2025 
158058000 PRE-BID CONFERENCE 11/13/2025  11/13/2025 
312010000 CONSTRUCTION 11/14/2025  04/30/2026 
196010000 FINAL ACCEPTANCE PAYMENT 05/01/2026  05/01/2026