Activity
|
Description
|
Planned
Start
|
Planned
Finish
|
164032000
|
PREPARE SCOPE OF WORK
|
03/16/2022 A
|
04/12/2022 A
|
256010000
|
ORDER DESIGN TRAFFIC
|
04/04/2022 A
|
04/07/2022 A
|
325010000
|
TIITF & OTHER GOV DOC
|
04/06/2022 A
|
04/22/2022 A
|
298010000
|
R/W ESTIMATE UPDATE
|
04/12/2022 A
|
06/06/2022 A
|
232032000
|
DESIGN CONSULTANT ADVERTISE
|
04/18/2022 A
|
04/18/2022 A
|
401032000
|
CONSULT SHORTLISTING
|
05/16/2022 A
|
05/16/2022 A
|
402032000
|
CONSULT FINAL SELECTION
|
06/27/2022 A
|
06/27/2022 A
|
450032000
|
TIP / STIP AMENDMENT
|
06/30/2022 A
|
07/22/2022 A
|
250010000
|
P.E. BEGIN
|
07/29/2022 A
|
07/29/2022 A
|
193320000
|
LOCAL FUNDS DEPOSITED
|
08/17/2022 A
|
02/06/2023 A
|
237032000
|
FHWA AUTHORITY RECEIVED
|
09/09/2022 A
|
09/09/2022 A
|
299032000
|
REQUEST FOR AUTHORIZATION
|
09/14/2022 A
|
09/14/2022 A
|
234032000
|
NOTICE TO PROCEED
|
09/21/2022 A
|
09/21/2022 A
|
233032000
|
P.E. CONTRACT EXECUTED
|
09/21/2022 A
|
09/21/2022 A
|
743000000
|
ON HOLD
|
09/28/2022 A
|
03/01/2023 A
|
290010000
|
COMMUNITY AWARE PLAN COMPLETE
|
10/06/2022 A
|
10/06/2022 A
|
274000000
|
SUBMIT BHR
|
01/11/2023 A
|
09/14/2023 A
|
106010000
|
DESIGN SURVEY
|
02/06/2023 A
|
04/28/2023 A
|
153010000
|
PAVEMENT SURVEY
|
02/06/2023 A
|
04/28/2023 A
|
132010000
|
ROADWAY SOILS REPORT
|
02/06/2023 A
|
09/14/2023 A
|
260010000
|
TYPICAL SECTION APPROVED
|
02/06/2023 A
|
11/20/2023 A
|
348020000
|
PARTNERSHIP MEETING
|
04/05/2023 A
|
04/25/2023 A
|
228010000
|
SUBMIT UTILITY DATA
|
04/20/2023 A
|
04/20/2023 A
|
197010000
|
PAVEMENT DESIGN
|
05/01/2023 A
|
05/01/2023 A
|
348030000
|
PARTNERSHIP MEETING
|
05/17/2023 A
|
07/21/2023 A
|
277000000
|
SUBMIT BDR
|
07/31/2023 A
|
09/14/2023 A
|
348040000
|
PARTNERSHIP MEETING
|
09/12/2023 A
|
01/15/2024 A
|
297020000
|
CONST. ESTIMATE UPDATE
|
10/27/2023 A
|
10/27/2023 A
|
277010000
|
SUBMIT BDR
|
10/27/2023 A
|
11/20/2023 A
|
274010000
|
SUBMIT BHR
|
10/27/2023 A
|
11/20/2023 A
|
323C20000
|
RETENTION/MITIGAT R/W REQRMTS
|
11/30/2023 A
|
02/19/2024 A
|
381000000
|
PREPARE PHI (30%) DESIGN PLN
|
01/16/2024 A
|
03/15/2024 A
|
270032000
|
SUBMIT BRIDGE PACKAGE
|
03/15/2024 A
|
03/15/2024 A
|
301010000
|
PHASE I PLANS REVIEW
|
03/18/2024 A
|
04/12/2024 A
|
297010000
|
CONST. ESTIMATE UPDATE
|
04/02/2024 A
|
04/02/2024 A
|
297030000
|
CONST. ESTIMATE UPDATE
|
04/02/2024 A
|
04/02/2024 A
|
106020000
|
DESIGN SURVEY
|
04/02/2024 A
|
04/09/2024 A
|
247010000
|
LOCAL GOVERNMENT AGREEMENT
|
04/15/2024 A
|
07/05/2024 A
|
382000000
|
PREPARE PHII (60%) DESIGN PLN
|
04/15/2024 A
|
11/22/2024 A
|
264010000
|
UTILITY CONTACT
|
04/16/2024 A
|
04/16/2024 A
|
132020000
|
ROADWAY SOILS REPORT
|
04/26/2024 A
|
11/22/2024 A
|
302010000
|
PHASE II PLANS REVIEW
|
11/25/2024 A
|
12/20/2024 A
|
333032000
|
CULTURAL RESOURCES ASSESS SURV
|
12/03/2024 A
|
04/01/2025 A
|
297060000
|
CONST. ESTIMATE UPDATE
|
12/19/2024 A
|
12/19/2024 A
|
383000000
|
PREPARE PHIII (90%) DESIGN PLN
|
12/23/2024 A
|
07/28/2025
|
184010000
|
SUBMIT BRDGE LOAD RATING
|
12/23/2024 A
|
07/28/2025
|
348010000
|
PARTNERSHIP MEETING
|
12/27/2024 A
|
12/27/2024 A
|
277020000
|
SUBMIT BDR
|
12/27/2024 A
|
12/27/2024 A
|
749000000
|
TYPE 1 CE APPROVAL
|
12/27/2024 A
|
12/29/2025
|
272010000
|
FILE PERMITS
|
01/31/2025 A
|
01/31/2025 A
|
272020000
|
FILE PERMITS
|
03/03/2025 A
|
10/03/2025
|
292010000
|
PUBLIC INFO MEETING
|
03/10/2025 A
|
03/10/2025 A
|
274020000
|
SUBMIT BHR
|
04/02/2025 A
|
04/02/2025 A
|
265010000
|
UTILITY PRE-DESIGN CONF
|
06/30/2025
|
07/28/2025
|
145010000
|
PERMITS
|
06/30/2025
|
Fiscal Year: 2027
|
217010000
|
USACE PERMIT
|
06/30/2025
|
Fiscal Year: 2027
|
751000000
|
SECTION 4(F)
|
07/10/2025
|
08/08/2025
|
182010000
|
REQUEST BRIDGE NUMBER
|
07/29/2025
|
08/22/2025
|
297090000
|
CONST. ESTIMATE UPDATE
|
07/29/2025
|
08/25/2025
|
303010000
|
PHASE III PLANS REVIEW
|
07/29/2025
|
08/25/2025
|
126010000
|
UTILITY RELOCATION
|
07/29/2025
|
Fiscal Year: 2027
|
182020000
|
REQUEST BRIDGE NUMBER
|
07/30/2025
|
08/25/2025
|
384000000
|
PREPARE PHIV (100%) DESIGN PLN
|
08/26/2025
|
12/01/2025
|
186010000
|
APPROVE BRDGE LOAD RATING
|
12/02/2025
|
12/29/2025
|
297100000
|
CONST. ESTIMATE UPDATE
|
12/02/2025
|
12/29/2025
|
310010000
|
PHASE IV PLANS REVIEW
|
12/02/2025
|
12/29/2025
|
130010000
|
SOIL CROSS SECTION
|
12/02/2025
|
12/29/2025
|
113070000
|
ROADWAY PLANS
|
12/30/2025
|
01/23/2026
|
172010000
|
CHECK LIST ACTIVITIES
|
03/13/2026
|
04/17/2026
|
220010000
|
UPDATE PLANS
|
03/16/2026
|
Fiscal Year: 2027
|
748000000
|
ENV DOC REEVAL-CONST ADVERTSMT
|
03/16/2026
|
Fiscal Year: 2027
|
193520000
|
LOCAL FUNDS DEPOSITED
|
06/05/2026
|
Fiscal Year: 2027
|
193620000
|
LOCAL FUNDS DEPOSITED
|
06/05/2026
|
Fiscal Year: 2027
|
189010000
|
FINAL REVIEW
|
06/08/2026
|
Fiscal Year: 2027
|
266010000
|
UTILITIES CERTIFIED
|
06/08/2026
|
Fiscal Year: 2027
|
171010000
|
REQUEST CONTRACT TIME
|
06/09/2026
|
Fiscal Year: 2027
|
222010000
|
ALL PERMITS CLEAR
|
06/29/2026
|
Fiscal Year: 2027
|
187010000
|
NO R/W REQRD CERTIFICATION
|
06/29/2026
|
Fiscal Year: 2027
|
279010000
|
RAILROAD CLEAR
|
06/29/2026
|
Fiscal Year: 2027
|
220020000
|
UPDATE PLANS
|
06/29/2026
|
Fiscal Year: 2027
|
205010000
|
CNST UTILITY CONTRACT EXECUTED
|
Fiscal Year: 2027
|
Fiscal Year: 2027
|
19352U000
|
LOCAL FUNDS DEPOSITED
|
Fiscal Year: 2027
|
Fiscal Year: 2027
|
323C80000
|
RETENTION/MITIGAT R/W REQRMTS
|
Fiscal Year: 2027
|
Fiscal Year: 2027
|
450052000
|
TIP / STIP AMENDMENT
|
Fiscal Year: 2027
|
Fiscal Year: 2027
|
376010000
|
ENVIRONMENTAL CLEAR/CERTIF
|
Fiscal Year: 2027
|
Fiscal Year: 2027
|
304010000
|
CORING
|
Fiscal Year: 2027
|
Fiscal Year: 2027
|
248010000
|
D.M.S APPROVAL
|
Fiscal Year: 2027
|
Fiscal Year: 2027
|
204010000
|
PRODUCTION DATE
|
Fiscal Year: 2027
|
Fiscal Year: 2027
|
226010000
|
PLANS TO DIST SPECS
|
Fiscal Year: 2027
|
Fiscal Year: 2027
|
242010000
|
SPECIFICATIONS
|
Fiscal Year: 2027
|
Fiscal Year: 2027
|
242020000
|
SPECIFICATIONS
|
Fiscal Year: 2027
|
Fiscal Year: 2027
|
405010000
|
CEI CONSULTANT ADVERTISE
|
Fiscal Year: 2027
|
Fiscal Year: 2027
|
406010000
|
CEI CONSULT SHORTLISTING
|
Fiscal Year: 2027
|
Fiscal Year: 2027
|
297040000
|
CONST. ESTIMATE UPDATE
|
Fiscal Year: 2027
|
Fiscal Year: 2027
|
242030000
|
SPECIFICATIONS
|
Fiscal Year: 2027
|
Fiscal Year: 2027
|
212010000
|
TRANSMIT PKG FOR LETTING
|
Fiscal Year: 2027
|
Fiscal Year: 2027
|
237052000
|
FHWA AUTHORITY RECEIVED
|
Fiscal Year: 2027
|
Fiscal Year: 2027
|
407010000
|
CEI CONSULT FINAL SELECTION
|
Fiscal Year: 2027
|
Fiscal Year: 2027
|
280TBD000
|
LETTING DATE
|
Fiscal Year: 2027
|
Fiscal Year: 2027
|
408010000
|
CEI ENCUMBERED
|
Fiscal Year: 2027
|
Fiscal Year: 2027
|
203010000
|
C.E.I. CONS. CONT. EXEC.
|
Fiscal Year: 2027
|
Fiscal Year: 2027
|