EMERGENCY INFORMATION FDOT Emergency Travel Alert: For information on the current situation, please visit the following page - Alerts.


State of Florida Department of Transportation logo
Florida Department of

TRANSPORTATION

FDOT OWPB - WP Reports; 5 Year Work Program Item Detail
Office of Work Program and Budget
Updated: 4/9/2025 9:15 PM

Five Year Work Program
Selection Criteria
 All in State 
 2025-2030 G1 
 Item Number:449079-1 




Scheduled Activities may or may not be confirmed dates and are subject to change without notice.
Please contact the Program Services Office at the appropriate District office for validation.
 
449079-1 SPRINGHILL ROAD OVER MUNSON SLOUGH BRIDGE NO 550054
District 03 - Leon County
 
Project Manager: SHAWN JUSTICE
Type of Work: BRIDGE REPLACEMENT
Activity Description Planned
Start
Planned
Finish
164032000 PREPARE SCOPE OF WORK 03/16/2022 A 04/12/2022 A
256010000 ORDER DESIGN TRAFFIC 04/04/2022 A 04/07/2022 A
325010000 TIITF & OTHER GOV DOC 04/06/2022 A 04/22/2022 A
298010000 R/W ESTIMATE UPDATE 04/12/2022 A 06/06/2022 A
232032000 DESIGN CONSULTANT ADVERTISE 04/18/2022 A 04/18/2022 A
401032000 CONSULT SHORTLISTING 05/16/2022 A 05/16/2022 A
402032000 CONSULT FINAL SELECTION 06/27/2022 A 06/27/2022 A
450032000 TIP / STIP AMENDMENT 06/30/2022 A 07/22/2022 A
250010000 P.E. BEGIN 07/29/2022 A 07/29/2022 A
193320000 LOCAL FUNDS DEPOSITED 08/17/2022 A 02/06/2023 A
237032000 FHWA AUTHORITY RECEIVED 09/09/2022 A 09/09/2022 A
299032000 REQUEST FOR AUTHORIZATION 09/14/2022 A 09/14/2022 A
234032000 NOTICE TO PROCEED 09/21/2022 A 09/21/2022 A
233032000 P.E. CONTRACT EXECUTED 09/21/2022 A 09/21/2022 A
743000000 ON HOLD 09/28/2022 A 03/01/2023 A
290010000 COMMUNITY AWARE PLAN COMPLETE 10/06/2022 A 10/06/2022 A
274000000 SUBMIT BHR 01/11/2023 A 09/14/2023 A
106010000 DESIGN SURVEY 02/06/2023 A 04/28/2023 A
153010000 PAVEMENT SURVEY 02/06/2023 A 04/28/2023 A
132010000 ROADWAY SOILS REPORT 02/06/2023 A 09/14/2023 A
260010000 TYPICAL SECTION APPROVED 02/06/2023 A 11/20/2023 A
348020000 PARTNERSHIP MEETING 04/05/2023 A 04/25/2023 A
228010000 SUBMIT UTILITY DATA 04/20/2023 A 04/20/2023 A
197010000 PAVEMENT DESIGN 05/01/2023 A 05/01/2023 A
348030000 PARTNERSHIP MEETING 05/17/2023 A 07/21/2023 A
277000000 SUBMIT BDR 07/31/2023 A 09/14/2023 A
348040000 PARTNERSHIP MEETING 09/12/2023 A 01/15/2024 A
297020000 CONST. ESTIMATE UPDATE 10/27/2023 A 10/27/2023 A
277010000 SUBMIT BDR 10/27/2023 A 11/20/2023 A
274010000 SUBMIT BHR 10/27/2023 A 11/20/2023 A
323C20000 RETENTION/MITIGAT R/W REQRMTS 11/30/2023 A 02/19/2024 A
381000000 PREPARE PHI (30%) DESIGN PLN 01/16/2024 A 03/15/2024 A
270032000 SUBMIT BRIDGE PACKAGE 03/15/2024 A 03/15/2024 A
301010000 PHASE I PLANS REVIEW 03/18/2024 A 04/12/2024 A
297010000 CONST. ESTIMATE UPDATE 04/02/2024 A 04/02/2024 A
297030000 CONST. ESTIMATE UPDATE 04/02/2024 A 04/02/2024 A
106020000 DESIGN SURVEY 04/02/2024 A 04/09/2024 A
247010000 LOCAL GOVERNMENT AGREEMENT 04/15/2024 A 07/05/2024 A
382000000 PREPARE PHII (60%) DESIGN PLN 04/15/2024 A 11/22/2024 A
264010000 UTILITY CONTACT 04/16/2024 A 04/16/2024 A
132020000 ROADWAY SOILS REPORT 04/26/2024 A 11/22/2024 A
302010000 PHASE II PLANS REVIEW 11/25/2024 A 12/20/2024 A
333032000 CULTURAL RESOURCES ASSESS SURV 12/03/2024 A 04/01/2025 A
297060000 CONST. ESTIMATE UPDATE 12/19/2024 A 12/19/2024 A
383000000 PREPARE PHIII (90%) DESIGN PLN 12/23/2024 A 07/28/2025 
184010000 SUBMIT BRDGE LOAD RATING 12/23/2024 A 07/28/2025 
348010000 PARTNERSHIP MEETING 12/27/2024 A 12/27/2024 A
277020000 SUBMIT BDR 12/27/2024 A 12/27/2024 A
749000000 TYPE 1 CE APPROVAL 12/27/2024 A 12/29/2025 
272010000 FILE PERMITS 01/31/2025 A 01/31/2025 A
272020000 FILE PERMITS 03/03/2025 A 10/03/2025 
292010000 PUBLIC INFO MEETING 03/10/2025 A 03/10/2025 A
274020000 SUBMIT BHR 04/02/2025 A 04/02/2025 A
265010000 UTILITY PRE-DESIGN CONF 06/30/2025  07/28/2025 
145010000 PERMITS 06/30/2025  Fiscal Year: 2027
217010000 USACE PERMIT 06/30/2025  Fiscal Year: 2027
751000000 SECTION 4(F) 07/10/2025  08/08/2025 
182010000 REQUEST BRIDGE NUMBER 07/29/2025  08/22/2025 
297090000 CONST. ESTIMATE UPDATE 07/29/2025  08/25/2025 
303010000 PHASE III PLANS REVIEW 07/29/2025  08/25/2025 
126010000 UTILITY RELOCATION 07/29/2025  Fiscal Year: 2027
182020000 REQUEST BRIDGE NUMBER 07/30/2025  08/25/2025 
384000000 PREPARE PHIV (100%) DESIGN PLN 08/26/2025  12/01/2025 
186010000 APPROVE BRDGE LOAD RATING 12/02/2025  12/29/2025 
297100000 CONST. ESTIMATE UPDATE 12/02/2025  12/29/2025 
310010000 PHASE IV PLANS REVIEW 12/02/2025  12/29/2025 
130010000 SOIL CROSS SECTION 12/02/2025  12/29/2025 
113070000 ROADWAY PLANS 12/30/2025  01/23/2026 
172010000 CHECK LIST ACTIVITIES 03/13/2026  04/17/2026 
220010000 UPDATE PLANS 03/16/2026  Fiscal Year: 2027
748000000 ENV DOC REEVAL-CONST ADVERTSMT 03/16/2026  Fiscal Year: 2027
193520000 LOCAL FUNDS DEPOSITED 06/05/2026  Fiscal Year: 2027
193620000 LOCAL FUNDS DEPOSITED 06/05/2026  Fiscal Year: 2027
189010000 FINAL REVIEW 06/08/2026  Fiscal Year: 2027
266010000 UTILITIES CERTIFIED 06/08/2026  Fiscal Year: 2027
171010000 REQUEST CONTRACT TIME 06/09/2026  Fiscal Year: 2027
222010000 ALL PERMITS CLEAR 06/29/2026  Fiscal Year: 2027
187010000 NO R/W REQRD CERTIFICATION 06/29/2026  Fiscal Year: 2027
279010000 RAILROAD CLEAR 06/29/2026  Fiscal Year: 2027
220020000 UPDATE PLANS 06/29/2026  Fiscal Year: 2027
205010000 CNST UTILITY CONTRACT EXECUTED Fiscal Year: 2027 Fiscal Year: 2027
19352U000 LOCAL FUNDS DEPOSITED Fiscal Year: 2027 Fiscal Year: 2027
323C80000 RETENTION/MITIGAT R/W REQRMTS Fiscal Year: 2027 Fiscal Year: 2027
450052000 TIP / STIP AMENDMENT Fiscal Year: 2027 Fiscal Year: 2027
376010000 ENVIRONMENTAL CLEAR/CERTIF Fiscal Year: 2027 Fiscal Year: 2027
304010000 CORING Fiscal Year: 2027 Fiscal Year: 2027
248010000 D.M.S APPROVAL Fiscal Year: 2027 Fiscal Year: 2027
204010000 PRODUCTION DATE Fiscal Year: 2027 Fiscal Year: 2027
226010000 PLANS TO DIST SPECS Fiscal Year: 2027 Fiscal Year: 2027
242010000 SPECIFICATIONS Fiscal Year: 2027 Fiscal Year: 2027
242020000 SPECIFICATIONS Fiscal Year: 2027 Fiscal Year: 2027
405010000 CEI CONSULTANT ADVERTISE Fiscal Year: 2027 Fiscal Year: 2027
406010000 CEI CONSULT SHORTLISTING Fiscal Year: 2027 Fiscal Year: 2027
297040000 CONST. ESTIMATE UPDATE Fiscal Year: 2027 Fiscal Year: 2027
242030000 SPECIFICATIONS Fiscal Year: 2027 Fiscal Year: 2027
212010000 TRANSMIT PKG FOR LETTING Fiscal Year: 2027 Fiscal Year: 2027
237052000 FHWA AUTHORITY RECEIVED Fiscal Year: 2027 Fiscal Year: 2027
407010000 CEI CONSULT FINAL SELECTION Fiscal Year: 2027 Fiscal Year: 2027
280TBD000 LETTING DATE Fiscal Year: 2027 Fiscal Year: 2027
408010000 CEI ENCUMBERED Fiscal Year: 2027 Fiscal Year: 2027
203010000 C.E.I. CONS. CONT. EXEC. Fiscal Year: 2027 Fiscal Year: 2027