Activity
|
Description
|
Planned
Start
|
Planned
Finish
|
285038000
|
RFP/DES BUILD PKG APPROVAL
|
03/25/2024 A
|
03/27/2024 A
|
450038000
|
TIP / STIP AMENDMENT
|
04/24/2024 A
|
04/24/2024 A
|
874038000
|
LOCAL SIGNATURE
|
05/31/2024 A
|
05/31/2024 A
|
874138000
|
LOCAL SIGNATURE
|
05/31/2024 A
|
05/31/2024 A
|
250010000
|
P.E. BEGIN
|
07/01/2024 A
|
07/01/2024 A
|
449038000
|
LAP PH 28 PD&E AUTHORIZATION
|
07/29/2024
|
05/09/2025
|
452010000
|
P.E. OTHER AGENCY ENCUMBER
|
08/06/2024
|
05/19/2025
|
247038000
|
LOCAL GOVERNMENT AGREEMENT
|
08/07/2024
|
05/20/2025
|
874238000
|
LOCAL SIGNATURE
|
08/08/2024
|
06/17/2025
|
200038000
|
PROJECT ADVERTISEMENT
|
09/06/2024
|
07/16/2025
|
462038000
|
SHORT LIST
|
10/04/2024
|
07/23/2025
|
402038000
|
CONSULT FINAL SELECTION
|
10/11/2024
|
07/24/2025
|
462238000
|
SHORT LIST
|
10/14/2024
|
08/14/2025
|
462338000
|
SHORT LIST
|
11/04/2024
|
08/15/2025
|
231038000
|
SUBMIT CONSULTANT PACKAGE
|
11/05/2024
|
09/12/2025
|
231138000
|
SUBMIT CONSULTANT PACKAGE
|
12/03/2024
|
09/15/2025
|
231238000
|
SUBMIT CONSULTANT PACKAGE
|
12/04/2024
|
09/22/2025
|
234038000
|
NOTICE TO PROCEED
|
12/11/2024
|
09/23/2025
|
381038000
|
PREPARE PHI (30%) DESIGN PLN
|
12/12/2024
|
10/21/2025
|
301038000
|
PHASE I PLANS REVIEW
|
01/09/2025
|
11/11/2025
|
382038000
|
PREPARE PHII (60%) DESIGN PLN
|
01/30/2025
|
12/09/2025
|
302038000
|
PHASE II PLANS REVIEW
|
02/27/2025
|
01/06/2026
|
749000000
|
TYPE 1 CE APPROVAL
|
02/27/2025
|
03/31/2026
|
333038000
|
CULTURAL RESOURCES ASSESS SURV
|
02/27/2025
|
04/14/2026
|
383038000
|
PREPARE PHIII (90%) DESIGN PLN
|
03/20/2025
|
02/03/2026
|
303038000
|
PHASE III PLANS REVIEW
|
04/17/2025
|
02/24/2026
|
384038000
|
PREPARE PHIV (100%) DESIGN PLN
|
05/08/2025
|
03/24/2026
|
310038000
|
PHASE IV PLANS REVIEW
|
06/05/2025
|
04/14/2026
|
285058000
|
RFP/DES BUILD PKG APPROVAL
|
02/02/2026
|
05/06/2026
|
874030000
|
LOCAL SIGNATURE
|
02/16/2026
|
05/13/2026
|
187010000
|
NO R/W REQRD CERTIFICATION
|
02/16/2026
|
Fiscal Year: 2027
|
874058000
|
LOCAL SIGNATURE
|
02/23/2026
|
06/10/2026
|
748000000
|
ENV DOC REEVAL-CONST ADVERTSMT
|
04/01/2026
|
06/23/2026
|
450058000
|
TIP / STIP AMENDMENT
|
04/01/2026
|
Fiscal Year: 2027
|
376010000
|
ENVIRONMENTAL CLEAR/CERTIF
|
06/24/2026
|
06/24/2026
|
449058000
|
LAP PH 28 PD&E AUTHORIZATION
|
Fiscal Year: 2027
|
Fiscal Year: 2027
|
455010000
|
C.E.I. OTHER AGENCY ENCUMBER
|
Fiscal Year: 2027
|
Fiscal Year: 2027
|
454010000
|
CONSTRUCT OTHR AGENCY ENCUMBER
|
Fiscal Year: 2027
|
Fiscal Year: 2027
|
247058000
|
LOCAL GOVERNMENT AGREEMENT
|
Fiscal Year: 2027
|
Fiscal Year: 2027
|
874068000
|
LOCAL SIGNATURE
|
Fiscal Year: 2027
|
Fiscal Year: 2027
|
200010000
|
PROJECT ADVERTISEMENT
|
Fiscal Year: 2027
|
Fiscal Year: 2027
|
400010000
|
CEI CONSULT. ACTIVITIES
|
Fiscal Year: 2027
|
Fiscal Year: 2027
|
289010000
|
LAP LETTING
|
Fiscal Year: 2027
|
Fiscal Year: 2027
|
405010000
|
CEI CONSULTANT ADVERTISE
|
Fiscal Year: 2027
|
Fiscal Year: 2027
|
189058000
|
FINAL REVIEW
|
Fiscal Year: 2027
|
Fiscal Year: 2027
|
158058000
|
PRE-BID CONFERENCE
|
Fiscal Year: 2027
|
Fiscal Year: 2027
|
400030000
|
CEI CONSULT. ACTIVITIES
|
Fiscal Year: 2027
|
Fiscal Year: 2027
|
400020000
|
CEI CONSULT. ACTIVITIES
|
Fiscal Year: 2027
|
Fiscal Year: 2027
|
400040000
|
CEI CONSULT. ACTIVITIES
|
Fiscal Year: 2027
|
Fiscal Year: 2027
|
400050000
|
CEI CONSULT. ACTIVITIES
|
Fiscal Year: 2027
|
Fiscal Year: 2027
|
400060000
|
CEI CONSULT. ACTIVITIES
|
Fiscal Year: 2027
|
Fiscal Year: 2027
|
400070000
|
CEI CONSULT. ACTIVITIES
|
Fiscal Year: 2027
|
Fiscal Year: 2027
|
400080000
|
CEI CONSULT. ACTIVITIES
|
Fiscal Year: 2027
|
Fiscal Year: 2027
|
234068000
|
NOTICE TO PROCEED
|
Fiscal Year: 2027
|
Fiscal Year: 2027
|
400090000
|
CEI CONSULT. ACTIVITIES
|
Fiscal Year: 2027
|
Fiscal Year: 2027
|
312010000
|
CONSTRUCTION
|
Fiscal Year: 2027
|
Fiscal Year: 2028
|
196010000
|
FINAL ACCEPTANCE PAYMENT
|
Fiscal Year: 2028
|
Fiscal Year: 2028
|